|

Shuttle Information
History
of the Space Shuttle
Orbiter Vehicles
Countdown OnLine
Latest
Shuttle Manifest
Mixed Fleet Launch Schedule
Shuttle Reference Manual
Approach and Landing Tests
Shuttle Mission Archive Index
|
|

|
Main Propulsion Test Article (MPTA-098) |
The Main Propulsion Test Article (MPTA-098) consisted of an Orbiter aft-fuselage, a trus arrangement which simulated the Orbiter mid-fuselage and a complete Space Shuttle Main Engine
(SSME) thrust structure including all main propulsion system plumbing and electrical systems. The unit was shipped to the National Space Technology Laboratory
(NSTL) on 06/24/77 where it was mated with the Main Propulsion Test Article External Tank
(MPTA-ET) and used for static engine tests. The MPTA-ET is now located at the Marshall Space Flight Center
(MSFC) Alabama Space and Rocket Center where it is mounted to the "Orbiter Simulator"
Pathfinder while MPTA-098 is at the Stennis Space Center
(SSC) in Mississippi (previously called the NSTL).
On 7/2/79, MPTA-098 suffered major structural damage due to a fractured fuel valve on engine 2002. Testing resumed two months later but a liquid oxygen high speed turbopump failed 9.7 seconds into a scheduled 510 second test. It wasn't until 12/17/79 that a complete static firing was accomplished that included 3 main engines running up to 100 percent of rated thrust for 554 seconds.
On 1/17/81, just three months prior to the scheduled STS-1 launch date, MPTA-098 successfully demonstrated a 625 second firing. The three flight rated engines from
Columbia were removed, shipped to
NSTL, and installed on MPTA-098 where they successfully completed a 520-second flight mission demonstration test. The engines were then shipped back to KSC and installed on
Columbia where they successfully performed a 20-second Flight Readiness Firing
(FRF) on 2/20/81. This cleared the way for the launch of STS-1 on 4/12/81.
|
|
|
July
26, 1972
Contract Award
|
July
17, 1974
Start of long lead fabrication
|
June
24,1975
Start structural assembly of aft-fuselage
|
|
January 23, 1976
Truss on dock at Rockwell Downey
|
March 17, 1976
Complete premate at Downey and delivered to Palmdale
|
May 3, 1976
Complete proof load test setup at Palmdale
|
June 29,
1976
Move truss assembly from Palmdale Building 294 to 295
|
July 8,
1976
MPTA-098 on dock at Downey
|
July 12, 1976
Start of Final Assembly
|
July
24, 1976
Complete MPTA-098 proof load test
|
May
27, 1977
Completed Final Assembly, Transport to Seal Beach
|
June 3, 1977
Transport from Seal Beach to NSTL
|
June
24, 1977
Arrival at NSTL for static firing
|
August
10, 1977
Arrival of MPTA-ET at NSTL
|
|
|
April
21, 1978
1st static firing (2.5 sec) |
May 19, 1978
2nd static firing (15 sec)
|
June
15, 1978
3rd static firing (50 sec)
|
|
July
7, 19/78
4th static firing (100 sec) |
May 4,
1979
5th static firing flight nozzles (1.5 sec)
|
June
12, 1979
5th static firing flight nozzles (54 sec)
|
|
October
24, 1979
6th static firing flight nozzles (scrubbed)
|
November
4, 1979
6th static firing flight nozzles (10 sec cutoff)
|
December
17, 1979
6th static firing non-flight (554 sec)
|
|
February
28, 1980
7th static firing non-flight (555 sec)
|
March
28, 1980
8th static firing non-flight (539 sec)
|
April 16, 1980
9th static firing non-flight (4.6 sec cutoff)
|
May 30, 1980
9th static firing non-flight (565 sec cutoff)
|
July 12, 1980
10th static firing flight nozzels (105 sec shutdown)
|
November 3, 1980
11th static firing flight nozzels (20 sec shutdown)
|
December 4, 1980
11th static firing non-flight (591 sec) |
January 17, 1981
12th static firing flight nozzels (625 sec)
|
|
|
|