KSC Homepages NASA HomepagesJohn F. Kennedy Space Center - Payload Status Online
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines


Wednesday, April 12, 1995

Previous April Next

Sun

Mon

Tues

Wed

Thur

Fri

Sat

            1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30            

KSC Public Affairs Contact: George Diller (fax 407-867-2692)
E-mail: George.Diller-1@ksc.nasa.gov  

GOES-J/AC-77 
May 19 1:42 a.m. EDT 

The AC-77 Centaur stage was successfully mated to the Atlas today. Atlas 1 launch vehicle arrived at Cape Canaveral Air Station by C-5 air cargo plane on April 7. The following day it was offloaded and taken to Hangar J for receiving inspections. The Atlas first stage was erected on Pad 36-B on Monday. Pad crews yesterday were unable to hoist the Centaur stage atop the Atlas due to wind exceeding the 11 knot limit and because of a problem with ground support equipment. 

Due to a shipping mishap during ground transportation, the arrival of the AC-77 fairing is expected to be delayed by several days so that the fairing can be removed from its shipping container and inspected. 

The GOES-J weather satellite continues to undergo final processing at Astrotech and remains on schedule. Battery charging and reconditioning for launch has been completed and preparations are underway for installing them on the spacecraft. Thruster system cleaning and checkout has also been completed. A helium signature leak check of the spacecraft propulsion system has also been performed. A pressurization test of the propulsion system is currently underway. Spacecraft mechanical closeouts will begin later this week and are expected to be complete Apr. 20. 

Spacelab-MIR/STS-71 
Atlantis/June 

The tunnel connecting the Spacelab-MIR laboratory module with the crew compartment was installed last Thursday. During leak checks the following day it was found the tunnel would not hold pressure. Over the weekend the tunnel was demated and a piece of thermal blanket exterior insulation was found caught in the flange. It was removed, new seals were installed, and the tunnel was reconnected. The leak check was successful. 

On Saturday the STS-71 astronauts inspected the Spacelab-MIR laboratory modue as part of the Crew Equipment Interface Test. Changes or suggestions recommended by the crew are being implemented this week. 

Today the Spacelab module and the crew compartment are fully pressurized for a leak check. Final closeouts will begin tomorrow. This includes a final cleaning, documentation photography and removal of access platforms. Outside the module the mission flags and emblems will be installed. Payload bay door closure is scheduled for Thursday night. 

TDRS-G/STS-70 
Discovery/June 

At the Vertical Processing Facility (VPF), work on the TDRS-G Tracking and Data Relay Satellite has been running ahead of schedule. Standalone checkout of the spacecraft was completed yesterday. Mechanical mating of TDRS-G to the IUS upper stage booster was performed today, one day ahead of planning. The electrical connections will be established next week and will be followed by an Interface Verification Test (IVT) on Apr. 19. 

The STS-70 astronauts will conduct an inspection of the satellite on Saturday. Next Monday, April 17, the White Sands Compatibility Test will be performed. Data will flow from the TDRS-G satellite at the VPF through the associated TDRS-G ground station to a TDRS uplink antenna located at KSC’s MILA tracking station. Then, via an orbiting TDRS satellite, it will be relayed to the White Sands Ground Terminal in New Mexico for analysis. 

Also next week, CITE testing using the Cargo Integrated Test Equipment will be performed to assure the payload’s compatibility with the orbiter and readiness to be installed into Discovery’s payload bay. 

Wake Shield Facility/STS-69 
Endeavour/July 20 

At the NASA Hangar AE spacecraft checkout facility, the Wake Shield Facility was unpacked and inspected last week and test equipment was set up. The initial electrical systems testing is now complete and experiment integration is beginning. 

USML-2/STS-73 
Columbia/Sept. 21 

Retest of the Geophysical Fluids Flow Cell (GFFC) experiment after repair has been successful. Closeouts of the experiment racks continue. Seven out of ten racks are closed out and the remaining three should be closed out by the end of Friday. Preparations will then begin for installing the racks into the Spacelab module. A system test of the module was completed this week in preparation for the rack installation which is scheduled for April 19.


Table of Contents 

KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

07/31/2000

Curator: Kay Grinter (kay.grinter-1@ksc.nasa.gov) / InDyne, Inc
Web Development: JBOSC  Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director