GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORTGO TO THE NEXT SPACE SHUTTLE STATUS REPORT
SPACE SHUTTLE STATUS REPORT Wednesday, November 23, 1994 Vehicle: OV-103/Discovery Mission number: STS-63 Location: OPF Bay 2 Orbital altitude: 196 sm Primary payload: Spacehab-3/Spartan Inclination: 51.6 degrees Launch date: Feb. 2 12:51 a.m. Landing: Feb. 10 7:05 a.m. Mission duration: 8 days, 6 hrs. Crew Size: 6 STS-63 IN WORK: functional test of remote manipulator system forward reaction control system IVT orbiter mid-body closeouts checkout and servicing of water spray boiler system potable water servicing establishing main engine mechnical and electrical connections STS-63 WORK SCHEDULED: Spacehab tunnel/tunnel adapter leak test (Monday) move payload canister from O&C building to OPF Bay 2 (Monday) install Spacehab-3 laboratory module (next week) install Spartan payload (next week) install main engine heat shields (beginning Tuesday) STS-63 WORK COMPLETED: main engine installation installation of forward reaction control system ENDEAVOUR (STS-67) Astro-2 Functional testing of the orbital maneuvering system is occurring. Next week water spray boiler No. 3 is scheduled for installation. Window No. 6 will be removed and replaced and the other windows will be polished. Routine thermal protection system maintenance continues and the aft area tiles will be waterproofed. Also scheduled is testing of the orbiter's S-band and Ku-band communications systems. The navigation systems will also be tested including the TACAN, microwave scanning beam landing system (MSBLS) and the Global Positioning System (GPS) receiver. ATLANTIS (STS-71) MIR DOCKING Atlantis arrived in OPF bay 3 at 4:17 a.m. this morning after being towed from the mate-demate device at the Shuttle Landing Facility. Work to jack and level the orbiter and to establish access is in work. The orbiter/MIR docking adapter is scheduled to arrive at the Shuttle Landing Facility tonight between 8 and 9 p.m. If the arrival occurs before 9 p.m. it will be offloaded and transported to the Vehicle Assembly Building. If arrival should occur after that time offloading will occur on Friday. KSC 24-Hour Weather Summary Today's minimum temperature: 62 degrees Yesterday's maximum temperature: 80 degrees Lowest relative humidity: 64 percent Peak wind speed: NW-23 mph Precipitation as of 7 a.m.: 0 Total November precipitation: 10.05 inches