GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT FRIDAY, APRIL 7, 1995 (10:35 AM EST) NOTE: Missions STS-71 and STS-70 are both being targeted for no earlier than launch dates and options are being protected for each to be the next one launched. A more firm decision is expected within the next two weeks. MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 3 * TARGET LAUNCH DATE: June 10 (no earlier than) * APPROX. LAUNCH TIME: 10:12 p.m. LAUNCH WINDOW: 5 minutes * KSC LANDING DATE/TIME: June 21 at 5:41 p.m. MISSION DURATION: 10 days, 19 hours, 31 minutes CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees * Change from earlier report IN WORK TODAY: Aft engine compartment close-outs Install main engine heatshields Spacelab close-outs Tunnel leak checks Preparations for crew equipment interface test KEY OPERATIONAL MILESTONES (dates are targeted only): Crew equipment interface test (April 8-9) Final payload bay closure (April 13) Roll to Vehicle Assembly Building (April 19) Roll to Launch Pad 39-A (April 25) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 2 *TARGET LAUNCH DATE: June 8 (no earlier than) *APPROX. LAUNCH TIME: 10:23 a.m. LAUNCH WINDOW: 2 hours, 30 minutes *TARGET KSC LANDING DATE/TIME: June 16 at 8:33 a.m. MISSION DURATION: 8 days CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees * Change from earlier report NOTE: Discovery will not be transferred to the VAB for temporary storage but will remain in OPF bay 2 for an accelerated flow schedule to meet an earlier targeted launch date. The accelerated flow is made possible by not going to the VAB. IN WORK TODAY: Auxiliary power unit leak and functional checks Water spray boiler checks Solid rocket booster stacking operations in Vehicle Assembly Building high bay 3 WORK COMPLETED: Ammonia servicing Landing gear checks KEY OPERATIONAL MILESTONES (dates are targeted only): Install main engines (April 17) Roll to Vehicle Assembly Building (May 3) Roll out to pad 39 B (May 11) MISSION: STS-69 -- WSF-2 & SPARTAN 201-03 VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility bay 1 TARGET LAUNCH DATE: July 20 APPROX. LAUNCH TIME: 12:06 p.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: July 31 at 8:37 a.m. MISSION DURATION: 10 days, 21 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 190 statute miles/28.45 degrees IN WORK TODAY: Extended duration orbiter pallet demate preparations Preparations to remove main engines Functional checks of the forward reaction control system WORK SCHEDULED: Remove extended duration orbiter pallet (April 11) NOTE: The orbiter Columbia is expected to begin its ferry flight from Palmdale, Calif., to KSC on April 11 with an arrival at the Shuttle Landing Facility targeted for mid-day April 12. Columbia has spent the last six months undergoing structural inspections and modifications at the Rockwell facility in Palmdale. Columbia’s next mission is STS-73, a 16-day flight targeted for launch in September. Upon arrival, Columbia will be stored temporarily in the Vehicle Assembly Building until Atlantis is rolled out of the Orbiter Processing Facility for external tank mating operations.

      GO TO THE STATUS REPORTS HOME PAGE