      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT TUESDAY, FEBRUARY 21, 1995 (12:06 PM EST) MISSION: STS-67 -- ASTRO-2 VEHICLE: Endeavour/OV-105 LOCATION: Pad 39A LAUNCH DATE and TIME: March 2 at 1:37 a.m. LAUNCH WINDOW: 2 hours, 30 minutes KSC LANDING DATE and TIME: March 17 at 3:09 p.m. MISSION DURATION: 15 days, 13 hours, 32 minutes CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 218 statute miles/28.45 degrees IN WORK TODAY: Close outs of aft engine compartment Preparations for ordnance operations WORK COMPLETED: Load hypergolic fuels KEY OPERATIONAL MILESTONES: Ordnance installation (tonight) Close payload bay doors for flight (Feb. 24) Crew arrival at KSC (11:15 p.m. Feb. 26) Begin countdown for March 2 launch (2 a.m. Feb. 27) MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH PERIOD: May/June APPROX. LAUNCH PERIOD: late night LAUNCH WINDOW: 5 minutes KSC LANDING DATE/TIME: TBD MISSION DURATION: 9 days, 20 hours CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees IN WORK TODAY: Install main engine no. 2 Remove and replace Freon/water interchanger Stack solid rocket boosters in Vehicle Assembly Building high bay 1 WORK COMPLETED: Install main engines no. 1 and 3 Install main landing gear wheel and tire assemblies Install drag chute KEY OPERATIONAL MILESTONES (dates are targeted only): Install Orbiter Docking System (March 13) Install spacelab (March 17) Crew equipment interface test (April 11) Final payload bay closure (April 12) Roll to Vehicle Assembly Building (April 18) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: June 22 APPROX. LAUNCH TIME: 11:13 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: June 30 at 9:23 a.m. MISSION DURATION: 8 days CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees IN WORK TODAY: Clear bay to off-load hypergolic reactants WORK COMPLETED: Remove Spacehab and SPARTAN payloads and transfer to Operations and Checkout Building Post-flight toxic vapor checks near and around auxiliary power units Final destow of spacehab experiments WORK SCHEDULED: Remove space shuttle main engines (March 3)

      GO TO THE STATUS REPORTS HOME PAGE