KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT MONDAY, JULY 31, 1995 (12:14 PM EDT) MISSION: STS-69 -- WSF-2 & SPARTAN 201-03 VEHICLE: Endeavour/OV-105 LOCATION: Pad 39-A TARGET LAUNCH DATE/TIME: NET Mid-Aug. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: TDB MISSION DURATION: 10 days, 20 hours, 29 minutes CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 230 statute miles/28.45 degrees NOTE: Mission managers decided late last Friday to place the launch of Endeavour on indefinite hold in order to finish a review of flight hardware associated with O-ring seals in a nozzle joint of the solid rocket boosters. During the next several days, engineers will determine what additional work and inspections are necessary to alleviate concerns which came out of post-flight assessments of boosters used for the last two Shuttle launches. After reviewing the data from these missions, no concerns with the booster design were found. However, engineers will focus on the techniques used to apply a thermal barrier called RTV (Room Temperature Vulcanizer) around the O-ring seal in the nozzles. Managers expect to receive another briefing by the end of this week. IN WORK TODAY: * Orbiter aft engine compartment close-outs WORK COMPLETED: * Close payload bay doors for flight KEY OPERATIONAL MILESTONES (dates are target only): * Install ordnance and pressurize hypergolic reactant tanks (TBD) * Crew arrival (TBD) * Begin countdown for launch (TBD) MISSION: STS-73 -- U.S. MICROGRAVITY LABORATORY-2 VEHICLE: Columbia/OV-102 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH DATE/TIME: Sept. 21 at 9:31 a.m. EDT LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: Oct. 7 at 7:25 a.m. MISSION DURATION: 15 days, 22 hours CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 172 statute miles/39 degrees IN WORK TODAY: * Aft engine compartment and orbiter mid-body close-outs KEY OPERATIONAL MILESTONES (dates are target only): * Close payload bay doors (Aug. 4) * Roll to Vehicle Assembly Building (Aug. 16) MISSION: STS-74 -- 2nd MIR DOCKING (Docking Module) VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE/TIME: Oct. 26 at 3:08 p.m. EDT LAUNCH WINDOW: 7 minutes ESTIMATED MIR DOCKING DATE/TIME: Oct. 29 at 8:05 a.m. EST TARGET KSC LANDING DATE/TIME: Nov. 3 at 11:05 a.m. EST MISSION DURATION: 7 days, 20 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees NOTE: Preparations are underway to remove the forward reaction control system tomorrow and send it to the Hypergolic Maintenance Facility to replace a valve. KEY OPERATIONAL MILESTONES (dates are target only): * Remove drag chute hardware and forward reaction control system (Aug. 1) * Install robotic arm (Aug. 2) DISCOVERY/OV-103 -- Pre-Orbital Maintenance Down Period VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 1 TARGET DATE OF DEPARTURE FOR PALMDALE FOR OMDP: Sept. 26 NOTE: Discovery is scheduled to be delivered to Palmdale, Calif., for a nine-month Orbital Maintenance Down Period (OMDP). During this time, the vehicle will be outfitted with a 5th set of cryogenic tanks and an external airlock to support missions to the international Space Station. Discovery is scheduled to depart Kennedy Space Center via the 747 Shuttle Carrier Aircraft on or about Sept. 26. Discovery’s next flight, the second mission to service the Hubble Space Telescope, is targeted for launch in early 1997. This week, preparations are underway to remove the forward reaction control system and the main engines. KEY OPERATIONAL MILESTONES (dates are target only): * Remove forward reaction control system (Aug. 9) * Remove space shuttle main engines (Aug. 10)