      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT WEDNESDAY, JUNE 14, 1995 (2:17 PM EDT) MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Launch Pad 39-A TARGET LAUNCH DATE: June 23 (no earlier than) APPROX. LAUNCH TIME: 5:08 p.m. EDT LAUNCH WINDOW: 7 minutes TARGET KSC LANDING DATE/TIME: July 4 at 12:37 p.m. MISSION DURATION: 10 days (+1 day) CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees NOTE: Mission managers plan to select an official launch date for Atlantis later this week following a key spacewalk by Russian cosmonauts to inspect a set of solar arrays on the Mir space station. Launch at this time is planned for no earlier than June 23. IN WORK TODAY: * Ordnance operations * Aft engine compartment close-outs * Countdown preparations WORK COMPLETED: * Check-out contingency spacesuits * Close-out orbiter airlock KEY OPERATIONAL MILESTONES (dates are target only): * Complete aft engine compartment close-outs (June 16) * Begin countdown (TBD) * Crew arrival (TBD) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Vehicle Assembly Building high bay 3 LAUNCH DATE/TIME: July 13 at 9:41 a.m. LAUNCH WINDOW: 2 hours, 30 minutes KSC LANDING DATE/TIME: July 21 at 7:51 a.m. MISSION DURATION: 7 days, 22 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees NOTE: Work in the VAB to repair holes in the external tank’s foam insulation has been completed. The vehicle is set to be moved back to pad 39-B early tomorrow morning. IN WORK TODAY: * Preparations for rollout to pad 39-B WORK COMPLETED: * External tank foam insulation repairs KEY OPERATIONAL MILESTONES (dates are target only): * Return vehicle to pad 39-B (first motion currently set for 11:30 p.m. tonight) MISSION: STS-69 -- WSF-2 & SPARTAN 201-03 VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility bay 1 TARGET LAUNCH DATE/TIME: July 30 at 10:40 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: August 10 at 7:10 a.m. MISSION DURATION: 10 days, 20 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 230 statute miles/28.45 degrees NOTE: Close-outs of the orbiter’s mid-body and aft engine compartment continue today. KEY OPERATIONAL MILESTONES (dates are target only): * Close payload bay doors for move to Vehicle Assembly Building (June 15) * Roll orbiter to Vehicle Assembly Building (June 26) MISSION: STS-73 -- U.S. MICROGRAVITY LABORATORY-2 VEHICLE: Columbia/OV-102 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH DATE/TIME: Sept. 21 at 10:37 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: Oct. 7 at 8:31 a.m. MISSION DURATION: 16 days CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 172 statute miles/39 degrees NOTE: The forward reaction control system has been installed on the orbiter. The interface verification test is in work today.

      GO TO THE STATUS REPORTS HOME PAGE