GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT MONDAY, MARCH 20, 1995 (11:26 AM EST) MISSION: STS-67 -- ASTRO-2 VEHICLE: Endeavour/OV-105 LOCATION: Dryden Flight Research Facility, Edwards Air Force Base, Calif. LAUNCH DATE and TIME: March 2 at 1:38 a.m. EST EDWARDS LANDING DATE and TIME: Saturday, March 18 at 4:47 p.m. EST MISSION DURATION: 16 days, 15 hours, 08 minutes Endeavour’s KSC landing was waved off Friday due to low clouds, rain and thunderstorms at the Shuttle Landing Facility. Landing was rescheduled for Saturday on the first of three opportunities. Saturday’s KSC landing attempts were also waved off for reasons similar to those on Friday and mission managers decided to land Endeavour at Edwards Air Force Base, Calif. Endeavour landed at Edwards Air Force Base, Calif. runway 22 Saturday at 4:47 p.m. EST on orbit 263. The mission elapsed and landing times are: MET EST MAIN GEAR TOUCHDOWN 16:15:08:47 4:47:47 p.m. NOSE GEAR TOUCHDOWN 16:15:09:01 4:48:01 p.m. WHEELS STOP 16:15:09:46 4:48:46 p.m. MILES TRAVELED: 6.9 million (statue miles) Endeavour is in the mate-demate device at Dryden. Off-load of the residual cryogenics is complete and turnaround operations for ferry flight to KSC are in work. Managers anticipate being able to begin the ferry flight on Friday, March 24. MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH PERIOD: May/June APPROX. LAUNCH PERIOD: late night LAUNCH WINDOW: 5 minutes KSC LANDING DATE/TIME: TBD MISSION DURATION: 10 days, 19 hours, 31 minutes CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees IN WORK TODAY: Preparations to install main engines WORK COMPLETED: Orbiter Docking System/Atlantis integrated verification tests Potable water servicing Mate external tank with solid rocket boosters in Vehicle Assembly Building KEY OPERATIONAL MILESTONES (dates are targeted only): Flight crew at KSC for camera alignment checks (Tuesday) Install spacelab into orbiter (Wednesday) Install main engines (Thursday/Friday) Flight crew at KSC for Docking system test (March 29) Crew equipment interface test (April 8) Final payload bay closure (April 12) Roll to Vehicle Assembly Building (April 18) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: June 22 APPROX. LAUNCH TIME: 11:13 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: June 30 at 9:23 a.m. MISSION DURATION: 8 days CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees IN WORK TODAY: Main propulsion system leak and functional checks Orbital maneuvering system pod functional checks Mechanical and electrical checks of auxiliary power unit no. 2 WORK COMPLETED: Remove auxiliary power unit no. 2 Install drag chute External tank door functional checks WORK SCHEDULED: Payload premate tests

      GO TO THE STATUS REPORTS HOME PAGE