      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT WEDNESDAY, MARCH 22, 1995 (10:32 AM EST) MISSION: STS-67 -- ASTRO-2 VEHICLE: Endeavour/OV-105 LOCATION: Dryden Flight Research Facility, Edwards Air Force Base, Calif. KSC LAUNCH DATE and TIME: March 2 at 1:38 a.m. EST EDWARDS LANDING DATE and TIME: Saturday, March 18 at 4:47 p.m. EST MISSION DURATION: 16 days, 15 hours, 08 minutes Turnaround operations for Endeavour’s ferry flight back to Kennedy Space Center continue today at Edwards Air Force Base, Calif. Riding atop the modified 747 Shuttle Carrier Aircraft, Endeavour is scheduled to depart Edwards Friday morning with a probable return to KSC’s Shuttle Landing Facility mid-day Saturday. MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH PERIOD: May/June APPROX. LAUNCH PERIOD: late night LAUNCH WINDOW: 5 minutes KSC LANDING DATE/TIME: TBD MISSION DURATION: 10 days, 19 hours, 31 minutes CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees IN WORK TODAY: Transport spacelab from Operations and Checkout Building for installation into orbiter Preparations to install main engines Potable water servicing WORK COMPLETED: Orbiter Docking System center-line camera alignment checks Orbiter Docking System/Atlantis integrated verification tests KEY OPF OPERATIONAL MILESTONES (dates are targeted only): Install main engines (Thursday/Friday) Flight crew at KSC for Docking system test (March 28-29) Crew equipment interface test (April 8) Final payload bay closure (April 12) Roll to Vehicle Assembly Building (April 18) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: June 22 APPROX. LAUNCH TIME: 11:13 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: June 30 at 9:23 a.m. MISSION DURATION: 8 days CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees IN WORK TODAY: Bay closed for hazardous operations involving removing and replacing a thruster and auxiliary power unit no. 2 connections Solid rocket booster stacking operations in Vehicle Assembly Building high bay 3 WORK COMPLETED: Orbital maneuvering system pod functional checks Main propulsion system leak and functional checks Mechanical and electrical checks of auxiliary power unit no. 2 WORK SCHEDULED: Install main engines (March 27)

      GO TO THE STATUS REPORTS HOME PAGE