GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT THURSDAY, MARCH 23, 1995 (2:11 PM EST) MISSION: STS-67 -- ASTRO-2 VEHICLE: Endeavour/OV-105 LOCATION: Dryden Flight Research Facility, Edwards Air Force Base, Calif. KSC LAUNCH DATE and TIME: March 2 at 1:38 a.m. EST EDWARDS LANDING DATE and TIME: Saturday, March 18 at 4:47 p.m. EST MISSION DURATION: 16 days, 15 hours, 08 minutes Turnaround operations for Endeavour’s ferry flight back to Kennedy Space Center continue today at Edwards Air Force Base, Calif. Tonight the main engine tail cone will be installed and tomorrow the orbiter will be mated to the modified 747 Shuttle Carrier Aircraft. Endeavour is not scheduled to depart Edwards before Saturday morning with a probable return to KSC’s Shuttle Landing Facility mid-day Sunday, weather permitting. Winds and rain in California delayed work necessary for an earlier planned Friday departure. MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH DATE: June 2 (no earlier than) APPROX. LAUNCH TIME: 1:45 a.m. LAUNCH WINDOW: 5 minutes KSC LANDING DATE/TIME: June 12 at 9:15 p.m. MISSION DURATION: 10 days, 19 hours, 31 minutes CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees IN WORK TODAY: Begin space shuttle main engine installation Spacelab electrical mates to orbiter Potable water servicing WORK COMPLETED: Preparations to install main engines Install spacelab into orbiter Orbiter Docking System center-line camera alignment checks KEY OPF OPERATIONAL MILESTONES (dates are targeted only): Spacelab verification tests (Monday/Tuesday) Flight crew at KSC for Docking system test (Tuesday/Wednesday) Crew equipment interface test (April 8) Final payload bay closure (April 12) Roll to Vehicle Assembly Building (April 18) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: June 22 APPROX. LAUNCH TIME: 11:13 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: June 30 at 9:23 a.m. MISSION DURATION: 8 days CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees IN WORK TODAY: Bay closed for hazardous operations involving removing and replacing a thruster and auxiliary power unit no. 2 connections Solid rocket booster stacking operations in Vehicle Assembly Building high bay 3 WORK COMPLETED: Orbital maneuvering system pod functional checks Main propulsion system leak and functional checks Mechanical and electrical checks of auxiliary power unit no. 2 WORK SCHEDULED: Begin installation of space shuttle main engines (March 27)

      GO TO THE STATUS REPORTS HOME PAGE