GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORTGO TO THE NEXT SPACE SHUTTLE STATUS REPORT
KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT THURSDAY, MAY 18, 1995 (11:53 AM EDT) MISSION: STS-70 -- TDRS-G VEHICLE: Discovery/OV-103 LOCATION: Launch Pad 39-B TARGET LAUNCH DATE: June 8 * LAUNCH TIME: 10:20 a.m. EDT (9:01 a.m. for 5 day mission) LAUNCH WINDOW: 2 hours, 30 minutes * TARGET KSC LANDING DATE/TIME: June 16 at 8:18 a.m. (June 13 for 5 day flight) * MISSION DURATION: 7 days, 22 hours (with option to shorten to 5 days) CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees * NOTE: STS-70 launch time and mission duration will be determined by the Mission Management Team IN WORK TODAY: Helium signature test Payload/orbiter end-to-end test Terminal Countdown Demonstration Test (Thursday-Friday) WORK COMPLETED: Crew arrival for Terminal Countdown Demonstration Test Launch pad validations Mate orbiter mid-body umbilical unit to vehicle KEY OPERATIONAL MILESTONES (dates are target only): Pre-launch hypergolic propellant load (May 22-23) Launch readiness review (May 23) Flight readiness review (May 26) Begin orbiter engine compartment close-outs (May 30) Close payload bay doors for flight (June 5) Countdown begins (June 5) MISSION: STS-71 -- 1st MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Launch Pad 39-A TARGET LAUNCH DATE: June 22 (no earlier than) APPROX. LAUNCH TIME: 5:32 p.m. EDT LAUNCH WINDOW: 5 minutes TARGET KSC LANDING DATE/TIME: July 3 at 1 p.m. MISSION DURATION: 10 days, 19 hours, 31 minutes CREW SIZE: 7 up, 8 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees NOTE: Engineers have determined the need to remove and replace the high-pressure fuel turbo pump on space shuttle main engine no. 3. This work is scheduled for early next week and will not impact the target launch date. IN WORK TODAY: Preparations to remove and replace fuel turbo pump on main engine no. 3 WORK COMPLETED: Orbiter hydraulic connections Pre-launch hypergolic propellant load KEY OPERATIONAL MILESTONES (dates are target only): Terminal Countdown Demonstration Test (May 24-25) Space Shuttle main engine flight readiness test (May 30) Flight readiness review (June 2) Begin orbiter engine compartment close-outs (June 6) MISSION: STS-69 -- WSF-2 & SPARTAN 201-03 VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility bay 1 TARGET LAUNCH DATE/TIME: July 20 at 10:30 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: July 31 at 7:15 a.m. MISSION DURATION: 10 days, 21 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 190 statute miles/28.45 degrees NOTE: Preparations are underway to remove and replace the right-hand orbital maneuvering system pod early next week. Work to disconnect the pod from the orbiter is underway. KEY OPERATIONAL MILESTONES (dates are target only): Remove right hand orbital maneuvering system pod (May 23) Install Spartan payload into orbiter payload bay (May 24) Install replacement orbital maneuvering system pod (May 25) Crew equipment interface test (June 2) Roll orbiter to Vehicle Assembly Building (June 20) MISSION: STS-73 -- U.S. MICROGRAVITY LABORATORY-2 VEHICLE: Columbia/OV-102 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH DATE/TIME: Sept. 21 at 10:37 a.m. LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE/TIME: Oct. 7 at 8:31 a.m. MISSION DURATION: 16 days CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 167 statute miles/39 degrees NOTE: The left hand orbital maneuvering system pod has been installed on the orbiter and connections are currently in work.