KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT THURSDAY, NOVEMBER 2, 1995 (12:23 PM EST) Flight Day 14 MISSION: STS-73 -- U.S. MICROGRAVITY LABORATORY-2 VEHICLE: Columbia/OV-102 LOCATION: Orbit OFFICIAL LAUNCH DATE/TIME: Oct. 20 at 9:53 a.m. (EDT) TARGET KSC LANDING DATE/TIME: Nov. 5 at 6:54 a.m. (EST) MISSION DURATION: 15 days, 22 hours, 1 minute CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 172 statute miles/39 degrees NOTE: Landing opportunities at KSC on Sunday occur at 6:54 a.m. and 8:29 a.m. One landing opportunity is available at Edwards Air Force Base on Sunday at 9:55 a.m. (all times eastern) The STS-73 crew are: Commander Ken Bowersox; Pilot Kent Rominger; Mission Specialists Catherine Coleman, Michael Lopez-Alegria and Kathryn Thornton; and Payload Specialists Fred Leslie and Albert Sacco. MISSION: STS-74 -- 2nd MIR DOCKING (Docking Module) VEHICLE: Atlantis/OV-104 LOCATION: Pad 39A TARGET LAUNCH DATE/TIME: Nov. 11 at 7:56 a.m. LAUNCH WINDOW: 6 minutes, 57 seconds TARGET MIR DOCKING DATE/TIME: Nov. 14 at about 2:20 a.m. TARGET KSC LANDING DATE/TIME: Nov. 19 at about 1:28 p.m. MISSION DURATION: 8 days, 5 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees NOTE: Operations continue to prepare Atlantis for launch on Saturday, Nov. 11. If Columbia’s landing is delayed a day due to weather at KSC and at Edwards, managers anticipate having to delay the launch of Atlantis 24-hours. IN WORK TODAY: * Aft engine compartment close-outs * Close payload bay doors for flight WORK COMPLETED: * Install and check-out contingency space suits KEY STS-74 OPERATIONAL MILESTONES (dates are target only): * Ordnance installation and pressurize hypergolic system (Friday) * Launch countdown begins (7 a.m. Nov. 8) * Crew arrival (11 a.m. Nov. 8) MISSION: STS-72 -- SFU-Retrieval & OAST-Flyer VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility Bay 3 TARGET LAUNCH DATE/TIME: Jan. 11 at 4:18 a.m. EST LAUNCH WINDOW: 60 minutes TARGET KSC LANDING DATE/TIME: Jan. 20 at 2:54 a.m. MISSION DURATION: 8 days, 22 hours, 36 minutes CREW SIZE: 6 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees NOTE: The payload premate tests are complete and preparations are underway to install the OAST-Flyer payload into Endeavour’s payload bay Friday. The OAST-Flyer is being transported to the Orbiter Processing Facility today. KEY STS-72 OPERATIONAL MILESTONES (dates are target only): * Install OAST-Flyer payload into payload bay (Friday) * Mate external tank with solid rocket boosters in Vehicle Assembly Building (Nov. 9) * Final payload bay door closure (Nov. 21) * Roll to Vehicle Assembly Building (Nov. 29) All times eastern