KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT TUESDAY, NOVEMBER 7, 1995 (12:06 PM EST) MISSION: STS-74 -- 2nd MIR DOCKING (Docking Module) VEHICLE: Atlantis/OV-104 LOCATION: Pad 39A TARGET LAUNCH DATE/TIME: Nov. 11 at 7:56 a.m. LAUNCH WINDOW: 7 minutes TARGET MIR DOCKING DATE/TIME: Nov. 14 at about 2:20 a.m. TARGET KSC LANDING DATE/TIME: Nov. 19 at about 1:28 p.m. MISSION DURATION: 8 days, 5 hours CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees NOTE: Engineers have determined no additional work is required to verify the readiness for flight of the STS-74 solid rocket boosters in light of extremely small cracks found on hold-down posts attached to other boosters that flew earlier this year. Previous inspections on the boosters at the pad indicate no cracking is present. Mission managers will be fully briefed on the matter at the scheduled management team meeting to be held at KSC on Thursday. IN WORK TODAY: * Countdown preparations * Complete ordnance installation WORK COMPLETED: * Pressurize hypergolic propellant system * Aft engine compartment close-outs KEY STS-74 OPERATIONAL MILESTONES (dates are target only): * Launch countdown begins (7 a.m. Wednesday) * Crew arrival (11 a.m. Wednesday) MISSION: STS-72 -- SFU-Retrieval & OAST-Flyer VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility Bay 3 TARGET LAUNCH DATE/TIME: Jan. 11 at 4:18 a.m. EST LAUNCH WINDOW: 60 minutes TARGET KSC LANDING DATE/TIME: Jan. 20 at 2:54 a.m. MISSION DURATION: 8 days, 22 hours, 36 minutes CREW SIZE: 6 ORBITAL ALTITUDE and INCLINATION: 288 statute miles/28.45 degrees NOTE: The OAST-Flyer and Get Away Special canisters have been successfully installed in the orbiter’s payload bay. The payload interface verification test will begin today and continue through tomorrow. KEY STS-72 OPERATIONAL MILESTONES (dates are target only): * Mate external tank with solid rocket boosters in VAB (Thursday) * Install left hand orbital maneuvering system pod (Sunday) * Final payload bay door closure (Nov. 21) * Roll to Vehicle Assembly Building (Nov. 29) MISSION: STS-75 -- TETHERED SATELLITE-1R & USMP-3 VEHICLE: Columbia/OV-102 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: Feb. 29, 1996 (under review) TARGET KSC LANDING DATE: March 14, 1996 MISSION DURATION: 13 days, 16 hours CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees NOTE: The orbiter Columbia is in Orbiter Processing Facility bay 2 and post-mission assessments will continue today. A final assessment of tile damage resulting from the flight shows about 147 total hits, of which 26 had a major dimension of 1-inch or larger. KEY STS-75 OPERATIONAL MILESTONES (dates are target only): * Access aft engine compartment (Wednesday) * Open payload bay doors (Wednesday) * Remove USML payload (Friday) All times eastern