GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT WEDNESDAY, NOVEMBER 29, 1995 (2:12 PM EST) MISSION: STS-72 -- SFU-Retrieval & OAST-Flyer VEHICLE: Endeavour/OV-105 LOCATION: Orbiter Processing Facility Bay 3 TARGET LAUNCH DATE/TIME: Jan. 11 at 4:18 a.m. EST LAUNCH WINDOW: 60 minutes TARGET KSC LANDING DATE/TIME: Jan. 20 at 2:54 a.m. MISSION DURATION: 8 days, 22 hours, 36 minutes CREW SIZE: 6 ORBITAL ALTITUDE and INCLINATION: 288 statute miles/28.45 degrees NOTE: Endeavour’s rollover to the Vehicle Assembly Building has been delayed 24-hours due to problems encountered while lowering the orbiter onto the transporter and to allow extra time to finalize tests on the landing gear and associated electrical wiring. Move to the VAB is now set for no earlier than 8 a.m. tomorrow but more likely to occur around 12 noon. In the VAB, the orbiter will be mated to the external tank and solid rocket boosters. Rollout to pad 39B remains on schedule for Tuesday, Dec. 5. KEY STS-72 OPERATIONAL MILESTONES (dates are target only): * Roll to Vehicle Assembly Building (about 12 noon Thursday) * Rollout to pad 39B (Dec. 5) * Main engine flight readiness tests (Dec. 6-7) * Terminal Countdown Demonstration Test ( Dec. 11-12) MISSION: STS-75 -- TETHERED SATELLITE-1R & USMP-3 VEHICLE: Columbia/OV-102 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: Feb. 22 LAUNCH WINDOW: 2 hours, 30 minutes TARGET KSC LANDING DATE: March 7 MISSION DURATION: 13 days, 16 hours CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees NOTE: Work today includes servicing the Freon coolant loops on Columbia. The forward reaction control system has been removed from the orbiter and preparations are in work to transport it to the Hypergolic Maintenance Facility for post-flight assessments and to replace a faulty thruster. KEY STS-75 OPERATIONAL MILESTONES (dates are target only): * Install main engines (Dec. 12) * Install forward reaction control system (Dec. 19) MISSION: STS-76 -- 3rd MIR DOCKING VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 1 TARGET LAUNCH DATE: March 21 LAUNCH WINDOW: about 6 minutes TARGET KSC LANDING DATE: March 30 MISSION DURATION: 10 days (+1) CREW SIZE: 6 up -- 5 down ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees NOTE: Operations in work today include functional tests of the forward reaction control system and removal of the IMAX camera. The orbiter docking system will be removed later this week. KEY STS-76 OPERATIONAL MILESTONES (dates are target only): * Remove orbiter docking system (Dec. 2) * Remove main engines (Dec. 12) * Remove remote manipulator system (Dec. 12) All times eastern

      GO TO THE STATUS REPORTS HOME PAGE