GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      Friday, April 26, 1996
      
      George H. Diller
      
      
      Vehicle: OV-105/Endeavour
      Mission number: STS-77
      Location: Pad 39-B
      Primary payload:  Spacehab 4/Spartan 207/TEAMS
      Astronauts: 6   
      Orbital altitude: 176 statute miles
      Inclination: 39 degrees
      Mission Duration: 10 days, 0 hours, 37 minutes
      Launch date:   May 16   6:32 a.m. EDT
      Landing date:  May 26   7:09 a.m. EDT
      
      STS-77 IN WORK TODAY:
      -  Spacehab Interface Verification Test - Part 2
      -  External tank/solid rocket booster closeouts
      -  Orbiter avionics bay closeouts
      -  Flash evaporator system testing
      -  Sampling of potable water system
      -  Installation of solid rocket booster thermal curtains
            
      STS-77 WORK SCHEDULED NEXT WEEK:
      -  Loading of storable hypergolic propellants 
      -  Replenish launch pad liquid hydrogen and liquid oxygen storage tanks
      -  Spartan Interface Verification Test (IVT)
      -  Complete application of solid rocket booster aft skirt foam insulation
      -  Close payload bay doors for flight  
      
      STS-77 WORK COMPLETED:
      -  Spacehab Flight Crew Equipment Stowage
      -  Flush of potable water system
      
      NOTE:  Since all prelaunch activities are on schedule at this time, no work is 
      planned over the weekend.
        
                    
      STS-78/OV-102/Columbia
      Life and Microgravity Spacelab
      OPF Bay 2
      
      	Installation of the main engine heat shields is underway.  Electrical 
      connections between LMS and Columbia are continuing.  The tunnel adapter 
      installation has been rescheduled for Tuesday. The Interface Verification Test 
      (IVT) is scheduled for Monday and Tuesday next week. Orbiter avionics system 
      testing and associated mid-body closeouts continue.  In the Vehicle Assembly 
      Building, stacking of the forward assembly is tentatively scheduled for tonight.  
      Mating of the external tank to the solid rocket boosters has been rescheduled for 
      May 3.
      
      
      STS-79/OV-104/Atlantis
      MIR-4 Docking
      OPF Bay 1
      
      	Removal of the three main engines is underway today.  Brake inspections 
      are also being performed.  The functional test of the forward reaction control 
      system was completed yesterday and payload bay deconfiguration will be 
      completed today.  Rocketdyne engineers have successfully repeated the failure 
      of a main engine igniter from the last launch.  It works at ambient temperatures 
      but fails at 32 degrees Fahrenheit.  The igniter will be returned to the vendor.    
      
                                                   
      KSC 24-Hour Weather Summary
      Shuttle Landing Facility - 7 a.m.
      
      Today’s minimum temperature: 71 degrees
      Yesterday’s maximum temperature: 79 degrees
      Lowest relative humidity: 65 percent
      Peak wind speed/direction: 20 mph/E
      Precipitation: 0
      Total April precipitation: .55 inches
      Barometric pressure at 7 a.m.:  30.00 
      
      

      GO TO THE STATUS REPORTS HOME PAGE