GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      MONDAY, APRIL 29, 1996 (11:22 AM EDT)
      
      KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692)
      E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov
      
      
      MISSION: STS-77 -- SPACEHAB-4 & SPARTAN 207
      
      VEHICLE: Endeavour/OV-105
      LOCATION: Pad 39B
      TARGET LAUNCH DATE/TIME: May 16 at 6:32 a.m.
      LAUNCH WINDOW: 2 hours, 30 minutes
      TARGET KSC LANDING DATE/TIME: May 26 at 7:09 a.m.
      MISSION DURATION: 10 days
      CREW SIZE: 6
      ORBITAL ALTITUDE and INCLINATION: 176 statute miles/39 degrees
      
      NOTE:  The Spacehab interface verification test is complete. Today
      and tomorrow the pad will be closed to non-essential workers as
      hypergolic reactants are loaded into the orbiter’s reaction control
      system storage tanks.
      
      KEY STS-77 OPERATIONAL MILESTONES (dates are target only):
      * TEAMS payload interface verification test (Wednesday)
      * Spartan payload interface verification test (Thursday)
      * Close payload bay doors for flight (Friday)
      * Launch Readiness Review (Friday)
      * Begin orbiter aft engine compartment close-outs (May 6)
      * Flight Readiness Review (May 7)
      
      
      MISSION: STS-78 -- LIFE AND MICROGRAVITY SPACELAB (LMS)
      
      VEHICLE: Columbia/OV-102
      LOCATION: Orbiter Processing Facility bay 2
      TARGET LAUNCH DATE/TIME: June 20 at about 10:49 a.m.
      LAUNCH WINDOW: 2 hours, 30 minutes
      TARGET KSC LANDING DATE/TIME: July 6 at about 8:46 a.m.
      MISSION DURATION: 15 days, 22 hours
      CREW SIZE: 7
      ORBITAL ALTITUDE and INCLINATION: 173 statute miles/39 degrees
      
      NOTE: The Life and Microgravity Spacelab was installed into the
      orbiter’s payload bay last week. Electrical and mechanical mates are
      complete. The payload interface verification test is scheduled to
      begin today.
      
      KEY STS-78 OPERATIONAL MILESTONES (dates are target only):
      * Install tunnel adapter (Tuesday)
      * Final aerosurface checks and flight readiness test (May 3)
      * Roll orbiter to Vehicle Assembly Building (May 23)
      
      
      MISSION: STS-79 -- 4th MIR DOCKING
      
      VEHICLE: Atlantis/OV-104
      LOCATION:  Orbiter Processing Facility bay 1
      TARGET LAUNCH DATE: July 31 at about 11:42 p.m.
      LAUNCH WINDOW: 7-10 minutes
      TARGET KSC LANDING DATE: August 9 at about 8:17 p.m.
      MISSION DURATION: 8 days, 20 hours, 35 minutes
      CREW SIZE: 6
      ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees
      
      NOTE:	The Space Shuttle main engines have been removed. Testing of
      the orbiter’s main propulsion system continues this week. Also, a
      leak check of the no. 3 hydraulic pump is scheduled for later today.
      
      KEY STS-79 OPERATIONAL MILESTONES (dates are target only):
      * Install Space Shuttle main engines (May 20)
      
      

      GO TO THE STATUS REPORTS HOME PAGE