KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT THURSDAY, AUGUST 8, 1996 (12:12 PM EDT) KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692) E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov MISSION: STS-79 -- 4th MIR DOCKING & SPACEHAB DM VEHICLE: Atlantis/OV-104 LOCATION: Orbiter Processing Facility bay 3 TARGET LAUNCH DATE/TIME: September 12 at about 6:26 a.m. (EDT) LAUNCH WINDOW: 7-10 minutes TARGET KSC LANDING DATE/TIME: September 21 at about 11:30 a.m. MISSION DURATION: 9 days, 5 hours CREW SIZE: 6 ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees NOTE: Atlantis will remain on the orbiter transporter in the Orbiter Processing Facility until next week when it is scheduled to be returned to the VAB and mated with the new set of solid rocket boosters and external tank. The Spacehab (image) destow is complete and pressure decay checks are now in work. The external tank was demated today from STS-79's original set of SRBs. Destacking of the boosters is expected to begin as early as Monday. KEY STS-79 OPERATIONAL MILESTONES (dates are target only): Transport orbiter back to VAB and mate to new set of SRBs (Aug. 13) Roll out Space Shuttle to Pad 39A (Aug. 20) STS-79 Terminal Countdown Demonstration Test (Aug. 27-28) MISSION: STS-80 -- WAKE SHIELD FACILITY-3 and ORFEUS-SPAS-2 VEHICLE: Columbia/OV-102 LOCATION: Orbiter Processing Facility bay 1 TARGET LAUNCH DATE: (no earlier than) Oct. 31 at 2:40 p.m. (EST) LAUNCH WINDOW: 2 hours, 20 minutes TARGET KSC LANDING DATE/TIME: (no earlier than) Nov. 16 at 7:25 a.m. MISSION DURATION: 16 days CREW SIZE: 5 ORBITAL ALTITUDE and INCLINATION: 218 statute miles/28.45 degrees NOTE: Removal of Space Shuttle main engines is expected to begin tonight. Installation of the STS-80 main engines are scheduled to begin next Wednesday. KEY STS-80 OPERATIONAL MILESTONES (dates are target only): Begin removing Space Shuttle main engines (tonight) Complete installation of STS-80 main engines (about Aug. 15) NOTE: MISSION STS-81, ATLANTIS, IS TARGETED FOR LAUNCH ABOUT JAN. 16, 1997. SHUTTLE PROCESSING STATUS WILL BE ISSUED FOLLOWING MISSION STS-79. MISSION: STS-82 -- HUBBLE SPACE TELESCOPE SERVICING MISSION-2 VEHICLE: Discovery/OV-103 LOCATION: Orbiter Processing Facility bay 2 TARGET LAUNCH DATE: February 13, 1997 LAUNCH WINDOW: 61 minutes TARGET KSC LANDING DATE: February 23, 1997 MISSION DURATION: 9 days, 22 hours CREW SIZE: 7 ORBITAL ALTITUDE and INCLINATION: 360 statute miles/28.45 degrees NOTE: Auxiliary power unit hook-ups are scheduled to begin tonight as preparations to install the right hand orbital maneuvering system pod continue. The pod is scheduled to be installed early next week. KEY OPERATIONAL MILESTONES (dates are target only): Installation of right hand orbital maneuvering system pod (Aug. 13) Remote manipulator system installation complete (Aug. 20) Install forward reaction control system (about Aug. 30)-- end -- For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status" or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status" or "unsubscribe ksc-press-release.