      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT Thursday, August 22, 1996 George H. Diller Vehicle: OV-104/Atlantis Mission number: STS-79 Location: Pad 39-A Primary payload: Spacehab-Mir 4 Astronauts: 6 Orbital altitude: 245 statute miles Inclination: 51.6 degrees Mission Duration: 9 days, 5 hours, 5 minutes Target Launch date: Sept. 12 6:27 a.m. EDT Landing date: Sept. 21 11:36 a.m. EDT STS-79 IN WORK TODAY: - Spacehab and payload bay closeouts - Close payload bay doors for flight STS-79 WORK SCHEDULED: - Spacehab interface verification test (Friday) - Astronaut arrival for safety training and Terminal Countdown Demonstration Test (Aug. 25 5:30 p.m.) - KSC Launch Readiness Review (Aug. 26) - STS-79 Terminal Countdown Demonstration Test (Aug. 27 - 28) - Flight Readiness Review (Aug. 29) STS-79 WORK COMPLETED: - Established umbilical connections between Space Shuttle and launch pad - Established electrical and fluid connections between Spacehab and orbiter - Main engine flight readiness test - Forward bulkhead flood light inspections STS-79 ISSUES AND CONCERNS: None STS-80/OV-102/Columbia ORFEUS-SPAS 2/Wake Shield Facility 3 OPF Bay 1 The remote manipulator arm was installed last night and is being tested today. In the payload bay, the payload pre-mate electrical test is underway. Freon coolant loop testing is scheduled to begin Saturday. In processing activity next week, the waste containment system will be installed and checked out, the water spray boilers will be serviced and checked out, and the liquid hydrogen side of the main propulsion system will be leak checked. STS-82/OV-103/Discovery HST Second Servicing Mission OPF Bay 2 Testing of the auxiliary power units is complete. The cryogenic reactant system and leak and functional tests will be resumed next week. Installation of the data display units on the flight deck is underway today. Electrical connections are being installed between the orbiter and the right orbital maneuvering system pod. Preparations are beginning to remove and replace fuel cell No. 3 for a precautionary diaphragm replacement. In activity planned to occur next week, the thermal protection tiles will be waterproofed, the Ku-band antenna will be installed and tested, the S-band communications system will be checked out, the orbiter’s wheels and tires will be installed, a functional test of the star tracker door is planned, and the main propulsion system helium system leak and functional test will be performed. KSC 24-Hour Weather Summary Shuttle Landing Facility - 7 a.m. Today’s minimum temperature: 74 degrees Yesterday’s maximum temperature: 87 degrees Low relative humidity: 58 percent Peak wind speed/direction: 23 mph/NE Precipitation: .03 inches Total August precipitation: 5.17 inches Barometric pressure at 7 a.m.: 30.09

      GO TO THE STATUS REPORTS HOME PAGE