GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      

      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT


      KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT Friday, August 23, 1996 George H. Diller Vehicle: OV-104/Atlantis Mission number: STS-79 Location: Pad 39-A Primary payload: Spacehab-Mir 4 Astronauts: 6 Orbital altitude: 245 statute miles Inclination: 51.6 degrees Mission Duration: 9 days, 5 hours, 5 minutes Launch readiness date: Sept. 12 6:27 a.m. EDT Landing date: Sept. 21 11:36 a.m. EDT STS-79 IN WORK TODAY: - Spacehab/orbiter interface verification test (IVT) STS-79 WORK SCHEDULED: - Astronaut arrival for safety training and Terminal Countdown Demonstration Test (Aug. 25 5:30 p.m.) - KSC Launch Readiness Review (Aug. 26) - STS-79 Terminal Countdown Demonstration Test (Aug. 27 - 28) - Storable hyergolic propellant loading (Aug. 29) - Flight Readiness Review (Aug. 29) STS-79 WORK COMPLETED: - Closed payload bay doors for flight (5:40 p.m. Thursday) - Established electrical and fluid connections between Spacehab and orbiter - Main engine flight readiness test STS-79 ISSUES AND CONCERNS: None. All launch preparations are on schedule so no work is scheduled at the launch pad this weekend. The final launch date for STS-79 will be set at next Thursday’s Flight Readiness Review. STS-80/OV-102/Columbia ORFEUS-SPAS 2/Wake Shield Facility 3 OPF Bay 1 The right orbital maneuvering system pod begins functional testing today and will continue next week. The remote manipulator arm installation and checkout is complete. In the payload bay, the payload pre-mate electrical test continues. Freon coolant loop testing is scheduled to begin Saturday and will also continue next week. In other upcoming processing activity, the waste containment system will be installed and checked out, the water spray boilers will be serviced and tested, and the liquid hydrogen side of the main propulsion system will be leak checked. STS-82/OV-103/Discovery HST Second Servicing Mission OPF Bay 2 The orbiter’s star tracker is being installed today. Installation of the data display units on the flight deck is complete. Preparations are beginning to remove and replace fuel cell No. 3 for a precautionary diaphragm replacement. In processing activity planned to occur next week, the thermal protection tiles will be waterproofed, the Ku-band antenna will be installed and tested, the S-band communications system will be checked out, the orbiter’s wheels and tires will be installed, and the main propulsion system helium system leak and functional test will be performed. KSC 24-Hour Weather Summary Shuttle Landing Facility - 7 a.m. Today’s minimum temperature: 74 degrees Yesterday’s maximum temperature: 87 degrees Low relative humidity: 57 percent Peak wind speed/direction: 20 mph/ESE Precipitation: 0 Total August precipitation: 5.17 inches Barometric pressure at 7 a.m.: 30.17

      GO TO THE STATUS REPORTS HOME PAGE