STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)NOTE: Managers delayed yesterday's planned roll over activities to complete work on the nose landing gear strut. While the orbiter was being lowered, during weight and center of gravity checks, the strut retracted and demonstrated lower than normal pressure. The strut was repressurized and leak checks are complete and good.
Shuttle managers are also discussing the possibility of conducting inspections of "pyro can" bolts in Atlantis' aft compartment. The bolts, which hold an exterior covering for the pyrotechnic device that separates the orbiter from the external tank, had shown signs of slight elongation after a previous flight of the Space Shuttle Discovery (OV-103). A determination to conduct the inspection could delay Atlantis' roll over to the VAB by two days.
In the VAB, external tank and SRB postmating close-outs are in work and preparations continue for orbiter/ET mating this week.
STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-83R -- Microgravity Science Laboratory-1 (image)NOTE: Removal and replacement of fuel cell No. 1 continues today. Inspections of Columbia's main propulsion system continue and preparations are in work for main engine removal on Friday and Saturday. Functional checkout of the forward reaction control system is in work. The FRCS will be removed on Friday for thruster replacement work scheduled in the Hypergol Maintenance Facility.
STS-85 -- CRISTA-SPAS-2NOTE: The forward reaction control system was delivered to the OPF last week and is scheduled for installation next Monday. Water spray boiler checkouts continue. The payload bay doors are open and radiator inspections are in work today.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING and LOGISTICS MODULENOTE: Purge lines have been hooked up to Endeavour in the VAB and will remain in place until its transfer to OPF bay 3 on April 17. No work is scheduled for Endeavour while in the VAB.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/