KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      FRIDAY, AUGUST 1, 1997 (2:10 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: Joel.Wells-1@ksc.nasa.gov

      MISSION: STS-85 -- CRISTA-SPAS-2 (image)

      Index of STS-85 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Pad 39A
      • TARGET KSC LAUNCH DATE/TIME: August 7 at 10:41 a.m.
      • LAUNCH WINDOW: 1 hour, 39 minutes
      • TARGET KSC LANDING DATE/TIME: August 18 at 7:05 a.m.
      • MISSION DURATION: 10 days, 20 hours, 24 minutes
      • CREW: Brown, Rominger, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: Ordnance installation is complete and hypergolic propellant pressurization is in work through Saturday. Discovery's aft compartment close-outs will conclude on Saturday with installation of the aft access doors. Inspections of the orbiter's freon quick disconnect components are complete. Cryogenic loading of the CRISTA-SPAS payload is in work and launch countdown preparations continue on schedule.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Begin countdown (3 p.m. Aug. 4)
      • Crew arrival (5 p.m. Aug. 4)
      • Close payload bay doors for flight (Aug. 5)

      MISSION: STS-86 -- 7th MIR DOCKING & SPACEHAB DM
      • VEHICLE: Atlantis/OV-104
      • LOCATION: Orbiter Processing Facility bay 3
      • TARGET KSC LAUNCH DATE/TIME: September 18 at about 1:42 a.m. (under review)
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: September 28 at about 5:51 a.m. (under review)
      • MISSION DURATION: 10 days, 4 hours, 9 minutes
      • CREW: Wetherbee, Bloomfield, Parazynski, Titov, Chretien, Lawrence, Wolf (up), Foale (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Retests of Atlantis' oxidizer cross-feed line are complete. Aft compartment close-outs continue through Monday and structural leak checks are slated for Tuesday. Orbiter weight and center of gravity tests are scheduled for Thursday. Atlantis will be placed on the orbiter transfer vehicle next Friday in preparation for its Aug. 11 roll over to the Vehicle Assembly Building. Installation of thermal protection tiles for the forward reaction control system continues through next week. In the VAB, external tank/solid rocket booster close-outs continue through Tuesday.

      STS-86 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Orbiter roll to Vehicle Assembly Building (Aug. 11)
      • Roll Space Shuttle out to Pad 39A (Aug. 20)

      MISSION: STS-87 -- U.S. MICROGRAVITY PAYLOAD-4
      • VEHICLE: Columbia/OV-102
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: November 19 at 2:46 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: December 5 at 7:19 a.m.
      • MISSION DURATION: 15 days, 16 hours, 33 minutes
      • CREW: Kregel, Lindsey, Scott, Chawla, Doi, Kadenyuk
      • ORBITAL ALTITUDE and INCLINATION: 150 nautical miles/28.45 degrees

      NOTE: Deservicing of Columbia's freon coolant is loop No. 2 is in work today. Radiator inspections are under way. Work to deservice the orbiter's oxidizer cross-feed line is on hold while workers prepare for Shuttle main engine removal, slated to begin Aug. 6.

      STS-87 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Remove Space Shuttle main engines (Aug. 6)

      MISSION: STS-89 -- 8th MIR DOCKING & SPACEHAB DM

      Index of STS-89 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET KSC LAUNCH DATE/TIME: January 15, 1998 at about 12:57 a.m.
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: January 24, 1998 at about 5:20 a.m.
      • MISSION DURATION: 9 days, 4 hours, 23 minutes
      • CREW: Wilcutt, Edwards, Dunbar, Anderson, Reilly, Wolf (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Installation of fuel cell No. 1 is complete and workers will replace a connector on fuel cell No. 3 before completing installation. Modifications to the left and right-hand elevon coves are scheduled through tonight. The docking mechanism base installation is in work.

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      Go to the Previous Space Shuttle Status Report
      Go to the Next Space Shuttle Status Report

      Go to the Status Reports Home Page