STS-89 -- 8th MIR DOCKING & SPACEHAB DM
NOTE: In the Vehicle Assembly Building, the Shuttle Interface Test has been successfully completed. Sanding operations on a thin layer of the STS-89 external tank foam insulation are approximately 65% complete. Some additional work has been identified which may require an additonal one to two shifts of work. Managers are targeting Endeavour’s rollout from the VAB to Pad 39A for sometime Friday or perhaps early Saturday. The SPACEHAB payload is in the Payload Changeout Room at the pad awaiting Endeavour’s arrival. Once the Shuttle is on the launcher pedestals at the pad, electrical connections will be established and Endeavour’s payload bay doors will be opened. SPACEHAB installation is planned for this weekend.
STS-89 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-90 -- NEUROLABNOTE: Last night, technicians completed work to off-load Columbia’s residual hypergolic propellants. Functional tests on the forward reaction control system and remote manipulator system check-outs continue in work today. The RMS will be removed after testing is completed. Preparations will also begin at that time to remove and replace one of the payload bay floodlights. Post-flight inspections continue on Columbia’s thermal protection system (TPS), with more than 70 percent of the inspections complete. Managers expect to have an assessment on total tile damage and replacement requirements this week.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9th MIR DOCKING & SPACEHAB-SMNOTE: Functional tests on the orbiter maneuvering system continue on schedule. Radiator functional checks have been completed. Fuel cell monitoring modifications continue, water spray boiler servicing and body flap corrosion repairs also continue. Preparations are in work for aft flight deck reconfiguration and Modular Auxiliary Data System verifications.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/