KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      MONDAY, FEBRUARY 3, 1997 (11:29 AM EST)

      KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692)
      E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov

      MISSION: STS-82 -- HUBBLE SPACE TELESCOPE SERVICING MISSION-2
      • VEHICLE: Discovery/OV-103
      • LOCATION: Pad 39A
      • LAUNCH DATE/TIME: February 11 at 3:56 a.m.
      • LAUNCH WINDOW: 65 minutes
      • TARGET KSC LANDING DATE/TIME: February 21 at about 2:43 a.m.
      • MISSION DURATION: 9 days, 22 hours, 47 minutes
      • CREW: Bowersox, Horowitz, Lee, Hawley, Harbaugh, Smith, Tanner (image)
      • ORBITAL ALTITUDE and INCLINATION: 360 statute miles/28.45 degrees

      NOTE: Over the weekend, workers successfully removed and replaced the solid rocket booster nozzle plugs from the SRBs at the pad. Electrical hook-ups of the mission payloads are complete and cryogenic cooling of the Near Infrared Camera and Multi-Object Spectrometer (NICMOS) will continue through Wednesday morning. The payload interface verification test will begin this afternoon and the payload end-to-end test will start tomorrow. Aft engine compartment close-outs continue in work this week. The crew is scheduled to arrive at KSC Friday morning and the countdown is set to begin Saturday.

      STS-82 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Payload end-to-end test (Tuesday)
      • Ordnance installation and pressurization of hypergolic system (Thursday)
      • Crew arrival (8 a.m. Friday)
      • Close payload bay doors (Friday night)
      • Countdown begins (4 a.m. Saturday)
      • Complete aft engine compartment close-outs (Saturday)

      MISSION: STS-83 -- Microgravity Science Laboratory-1
      • VEHICLE: Columbia/OV-102
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET LAUNCH DATE/TIME: April 3 at 2:01 p.m. EST
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: April 19 at about 7:30 a.m. EDT
      • MISSION DURATION: 15 days, 16 hours, 29 minutes
      • CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch
      • ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees

      NOTE: Installation of the Space Shuttle main engines was completed this weekend. Also, the Microgravity Science Laboratory was installed into the payload bay on Saturday. Tunnel adapter installation is currently on hold pending engineering evaluation of a small dent found in a coolant tube in the payload bay. The right hand orbital maneuvering system pod has been delivered to the OPF and will be installed on the orbiter tomorrow.

      STS-83 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Begin OMS pod installation (Tuesday)
      • Crew equipment and interface test (CEIT) (Feb. 15)
      • Close payload bay doors for move to Vehicle Assembly Building (Feb. 24)
      • Roll to Vehicle Assembly Building (March 3)

      MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
      • VEHICLE: Atlantis/OV-104
      • LOCATION: Orbiter Processing Facility bay 3
      • OFFICIAL KSC LAUNCH DATE/TIME: May 15 at about 4:05 a.m. EDT
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: May 24 at about 7:50 a.m. EDT
      • MISSION DURATION: 9 days, 3 hours, 45 minutes
      • CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova
      • ORBITAL ALTITUDE and INCLINATION: 184 statute miles/51.6 degrees

      NOTE: Preparations continue to remove and replace auxiliary power unit (APU) No. 3. Over the weekend, the unit was disconnected and residual hypergolic reactants drained from the lines. The APU is scheduled to be replaced on Wednesday. Removal of the three Space Shuttle main engines is underway today and will be complete tomorrow. A functional check of the forward reaction control system is also in work in the OPF. Stacking of the solid rocket boosters for mission STS-84 has also begun in the VAB.

      STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Remove and replace APU No. 3 (Wednesday/Thursday)
      • Remove forward reaction control system (Feb. 8)
      • Install left hand orbital maneuvering system pod (Feb. 26)
      • Mate external tank to solid rocket boosters (Feb. 27)
      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm


      GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT
      GO TO THE STATUS REPORTS HOME PAGE