KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
MONDAY, FEBRUARY 24, 1997 (1:11 PM EST)
KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692)
E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov
MISSION: STS-83 -- Microgravity Science Laboratory-1
- VEHICLE: Columbia/OV-102
- LOCATION: Orbiter Processing Facility bay 1
- TARGET LAUNCH DATE/TIME: April 3 at about 2:01 p.m. EST
- LAUNCH WINDOW: 2 hours, 30 minutes
- TARGET KSC LANDING DATE/TIME: April 19 at about 7:30 a.m. EDT
- MISSION DURATION: 15 days, 16 hours, 29 minutes
- CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees
NOTE: Installation of the main engine heat shields is compete and aft
engine compartment close-outs continue. Final inspections and repairs to
the body-flap cove are continuing this week. Fuel cell voltage checks
also continue today. Final payload bay cleaning is expected to be
finished today followed by closing of the payload bay doors as early as
tonight.
STS-83 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Close payload bay doors for move to Vehicle Assembly Building (today)
- * Final landing gear functional check (Tuesday)
- * Roll to Vehicle Assembly Building (March 3)
MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
- VEHICLE: Atlantis/OV-104
- LOCATION: Orbiter Processing Facility bay 3
- TARGET KSC LAUNCH DATE/TIME: May 15 at about 4:05 a.m. EDT
- LAUNCH WINDOW: 7-10 minutes
- TARGET KSC LANDING DATE/TIME: May 24 at about 7:50 a.m. EDT
- MISSION DURATION: 9 days, 3 hours, 45 minutes
- CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees
NOTE: Closed-bay operations to remove and replace a faulty reaction
control system thruster is complete and close-outs of the orbital
maneuvering system is in work today. Installation of the left hand
orbital maneuvering engine actuator is also in work today. Stacking of
the solid rocket boosters in the Vehicle Assembly Building also
continues.
STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Install forward reaction control system (March 6)
- * Begin installation of Space Shuttle main engines (March 6-7)
- * Mate external tank to solid rocket boosters (March 10)
MISSION: STS-85 -- CRISTA-SPAS-2
- VEHICLE: Discovery/OV-103
- LOCATION: OPF bay 2
- TARGET LAUNCH DATE/TIME: July 17 at 10:04 a.m.
- LAUNCH WINDOW: TBD
- TARGET KSC LANDING DATE/TIME: July 28 at about 6:52 a.m.
- MISSION DURATION: 10 days, 20 hours, 48 minutes
- CREW: Brown, Ashby, Davis, Curbeam, Robinson, Tryggvason
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees
NOTE: Over the weekend, workers secured Discovery in the OPF and
completed the off-load of residual cryogenics in the onboard storage
tanks. Access to the vehicle's aft engine compartment and mid-body are
underway today. The payload bay doors will be opened later in the week
and the payloads removed next Monday.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Open payload bay doors (Thursday)
- * Remove payloads (March 3)
- * Complete off-load of residual hypergolic propellants (March 5)
--end--
For automatic e-mail subscriptions to this daily Shuttle
status report or KSC originated press releases, send an Internet
electronic mail message to domo@news.ksc.nasa.gov. In the body of the
message (not the subject line) type the words "subscribe
shuttle-status", or "subscribe ksc-press-release" (do not use
quotation marks). The system will reply with a confirmation via
e-mail of each subscription.
To remove your name from the list at any time, send an e-mail
address to domo@news.ksc.nasa.gov. In the body of the message (not
the subject line), type (no quotes) "unsubscribe shuttle-status", or
"unsubscribe ksc-press-release."
Status reports and other NASA publications are available on
the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
GO TO THE NEXT SPACE SHUTTLE STATUS REPORT
GO TO THE STATUS REPORTS HOME PAGE