KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      WEDNESDAY, FEBRUARY 26, 1997 (10:39 AM EST)

      KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692)
      E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov

      MISSION: STS-83 -- Microgravity Science Laboratory-1
      • VEHICLE: Columbia/OV-102
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET LAUNCH DATE/TIME: April 3 at 2:01 p.m. EST
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: April 19 at about 7:37 a.m. EDT
      • MISSION DURATION: 15 days, 16 hours, 36 minutes
      • CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees

      NOTE: The strong backs have been removed from the payload bay doors as preparations continue to roll Columbia to the VAB early next week. Final repairs to minor corrosion in the body-flap cove area are complete and close-outs are expected to be finished later today. Integrated hydraulic checks of the aerosurfaces and other orbiter systems will begin tonight. Aft engine compartment close-outs are also scheduled to be finished this weekend.

      STS-83 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      * Weight and center of gravity checks (Monday)
      * Roll to Vehicle Assembly Building and mate with external tank (March 4)
      * Roll out to Pad A (March 10)
      * Hot fire auxiliary power unit No. 2 (March 10)
      * Terminal Countdown Demonstration Test (TCDT) (March 13-14)

      MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
      • VEHICLE: Atlantis/OV-104
      • LOCATION: Orbiter Processing Facility bay 3
      • TARGET KSC LAUNCH DATE/TIME: May 15 at about 3:49 a.m.
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: May 24 at about 8:12 a.m.
      • MISSION DURATION: 9 days, 4 hours, 23 minutes
      • CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Decay checks on the power reactant and storage distribution system and close-outs of the orbital maneuvering system continue today. The European Proximity Sensor (EPS) payload has been installed and the interface verification test is scheduled to take place tomorrow. Stacking of the solid rocket boosters in the Vehicle Assembly Building also continues. Mate of the external tank to the solid rocket boosters is now scheduled for March 24.

      STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      * Install forward reaction control system (March 6)
      * Begin installation of Space Shuttle main engines (March 6-7)
      * Mate external tank to solid rocket boosters (March 24)

      MISSION: STS-85 -- CRISTA-SPAS-2
      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET LAUNCH DATE/TIME: July 17 at 10:06 a.m.
      • LAUNCH WINDOW: 1 hour, 54 minutes
      • TARGET KSC LANDING DATE/TIME: July 28 at about 6:54 a.m.
      • MISSION DURATION: 10 days, 20 hours, 48 minutes
      • CREW: Brown, Ashby, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: The payload bay doors will be opened tomorrow and the payloads removed next Monday. Flight crew systems destow and flight recorder down-loads are in work today. Final post-flight analysis indicates Discovery had a total of 103 impacts to its thermal protection system tiles during mission STS-82. Of those hits, only 18 were greater than one inch diameter, less than the average from previous missions.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      * Open payload bay doors (Thursday)
      * Remove payloads (March 3)
      * Complete off-load of residual hypergolic propellants (March 5)
      * Remove Space Shuttle main engines (March 28)
      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm


      GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT

      GO TO THE STATUS REPORTS HOME PAGE