NOTE: This is the first KSC Space Shuttle status for 1997. (There were no status reports issued from Dec. 19 - Jan. 1 due to the holidays.)
NOTE: Holiday outage deconfiguration is in work for all three orbiters at KSC. The payload bay doors were reopened today to gain access to the airlock C-hatch. Functional tests on C-hatch, scheduled for today, will conclude the hatch actuator testing on Atlantis. Main propulsion system tests are scheduled for tonight
Officials at NASA’s Marshall Space Flight Center recently approved the solid rocket booster nozzles for flight as is.
KEY STS-81 OPERATIONAL MILESTONES (dates are target only):
NOTE: Preparations to open the payload bay doors are in work. The Ku-band antenna retest and payload testing will continue today. Discovery’s aft compartment close-outs are also in work. In the VAB, preparations are in work to mate the orbiter to the external tank.
KEY STS-82 OPERATIONAL MILESTONES (dates are target only):
NOTE: Preparations are underway to open Columbia’s payload bay doors. STS-83 booster stacking operations continue in the VAB. The left aft booster has been mated and preparations are underway for stacking of the left aft center segment.
KEY STS-83 OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm