KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
MONDAY, JANUARY 27, 1997 (12:54 PM EST)
KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692)
E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov
MISSION: STS-82 -- HUBBLE SPACE TELESCOPE SERVICING MISSION-2
- VEHICLE: Discovery/OV-103
- LOCATION: Pad 39A
- TARGET LAUNCH DATE/TIME: February 11 at 3:56 a.m.
- LAUNCH WINDOW: 65 minutes
- TARGET KSC LANDING DATE/TIME: February 21 at about 2:43 a.m.
- MISSION DURATION: 9 days, 22 hours, 47 minutes
- CREW: Bowersox, Horowitz, Lee, Hawley, Harbaugh, Smith, Tanner
- ORBITAL ALTITUDE and INCLINATION: 360 statute miles/28.45 degrees
NOTE: Hypergolic loading operations are complete and a hot fire test
of the three auxiliary power units was successfully conducted Sunday
afternoon. The Rotating Service Structure will remain away from the
vehicle today as the payloads are installed into the pad's payload
change-out room. The payloads will be installed into the orbiter's
payload bay on Wednesday and the payload interface verification test
is set for this weekend.
STS-82 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- Extend Rotating Service Structure (about 9 a.m. Tuesday)
- Flight Readiness Review (Jan. 30)
- Payload interface verification test (Feb. 1)
MISSION: STS-83 -- Microgravity Science Laboratory-1
- VEHICLE: Columbia/OV-102
- LOCATION: Orbiter Processing Facility bay 1
- TARGET LAUNCH DATE/TIME: April 3 at 2:01 p.m. EST
- LAUNCH WINDOW: 2 hours, 30 minutes
- TARGET KSC LANDING DATE/TIME: April 19 at about 7:30 a.m. EDT
- MISSION DURATION: 15 days, 16 hours, 29 minutes
- CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch
- ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees
NOTE: The right hand orbital maneuvering system pod has been removed
from the orbiter. Wing-to-fuselage bolt torque checks are complete
and payload premate tests continue in work today. Stacking of the
right hand solid rocket booster in the Vehicle Assembly Building is
scheduled for completion this weekend.
STS-83 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- Install Space Shuttle main engines (Jan. 28)
- Install tunnel adapter into payload bay (Jan. 29)
- Install Microgravity Science Laboratory into orbiter's payload bay (Jan. 31)
- Mate external tank to solid rocket boosters in VAB (Jan. 29)
- Roll to Vehicle Assembly Building (March 3)
MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
- VEHICLE: Atlantis/OV-104
- LOCATION: Orbiter Processing Facility bay 3
- OFFICIAL KSC LAUNCH DATE/TIME: May 15 at about 4:05 a.m. EDT
- LAUNCH WINDOW: 7-10 minutes
- TARGET KSC LANDING DATE/TIME: May 24 at about 7:50 a.m. EDT
- MISSION DURATION: 9 days, 3 hours, 45 minutes
- CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova
- ORBITAL ALTITUDE and INCLINATION: 184 statute miles/51.6 degrees
NOTE: The payload bay doors will be opened today and access to the
aft engine compartment continues in work. Hydraulic operations to
position the aerosurfaces and main engines are complete. The Spacehab
payload is scheduled to be removed later this week.
STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- Remove Spacehab payload (Wednesday/Thursday)
--end--
For automatic e-mail subscriptions to this daily Shuttle
status report or KSC originated press releases, send an Internet
electronic mail message to domo@news.ksc.nasa.gov. In the body of the
message (not the subject line) type the words "subscribe
shuttle-status", or "subscribe ksc-press-release" (do not use
quotation marks). The system will reply with a confirmation via
e-mail of each subscription.
To remove your name from the list at any time, send an e-mail
address to domo@news.ksc.nasa.gov. In the body of the message (not
the subject line), type (no quotes) "unsubscribe shuttle-status", or
"unsubscribe ksc-press-release."
Status reports and other NASA publications are available on
the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
GO TO THE NEXT SPACE SHUTTLE STATUS REPORT
GO TO THE STATUS REPORTS HOME PAGE