STS-94 -- Microgravity Science Laboratory-1 (image)Take a of Columbia and the Microgravity Science Laboratory-1 Payload!
NOTE: Columbia continues to perform very well on orbit with more than half of the Microgravity Science Laboratory mission complete. Around-the-clock science investigations continue in the Spacelab module.
The crew of Mission STS-94: Commander Jim Halsell; Pilot Susan Still; Mission Specialists Janice Voss, Michael Gernhardt and Donald Thomas; and Payload Specialists Roger Crouch and Greg Linteris.
STS-85 -- CRISTA-SPAS-2 (image)
NOTE: In the VAB, orbiter/external tank mating operations continue with umbilical mates still in work. Functional testing of the liquid oxygen 17-inch disconnect began last night. The shuttle interface test is in work and continues through Friday. Discovery is slated to roll out to Pad 39A on Monday at about 2 a.m.
The CRISTA-SPAS payload was delivered to the pad early this morning and today is being installed into the Payload Changeout Room.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DM
NOTE: Shuttle main engine and main propulsion system integrated testing is complete and heat shield installation is in work. Fuel cell No. 2 mechanical mates are complete. Functional checks are also planned for Atlantis' liquid oxygen 17-inch disconnect.
Atlantis will undergo a routine, three-week modal or structural test beginning July 21. Because the test requires the orbiter's midbody to be closed for flight, the midbody portion of the Crew Equipment Interface Test (CEIT) has moved up to July 14. The forward portion of the CEIT is scheduled for July 26.
STS-86 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DMNOTE: Functional testing of Endeavour's upper airlock hatch is in work today. Replacement of window No. 6 concludes today. Modifications to the orbiter's elevon coves are on hold and will pickup again on Monday. Preparations to remove the 17-inch disconnect continue.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/