STS-85 -- CRISTA-SPAS-2 (image)
NOTE: The Terminal Countdown Demonstration Test (TCDT) began this morning in the Launch Control Center and at Pad 39A. Today, the astronauts are undergoing the customary safety training at the pad. Tomorrow, the crew will be on the flight deck of Discovery for the last three hours of the countdown dress rehearsal which will end at 11 a.m. The payload interface verification test has successfully concluded and preparations are now underway for servicing the CRISTA-SPAS with cryogenic helium next week. Preparations continue for loading hypergolic propellants aboard the Space Shuttle on Thursday.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DMNOTE: The thermal protection tiles for the forward reaction control system are being installed and the Shuttle's aft engine compartment close-outs continue in work. Close-outs of the crew cabin are now underway. In the VAB, external tank/SRB mate activities are scheduled for Thursday.
STS-86 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-87 -- U.S. MICROGRAVITY PAYLOAD-4NOTE: The payload bay doors are being opened today and preparations to remove the MSL-1 Spacelab module are in work. The tunnel adapter will be removed on Thursday. Post-flight access to the main engine compartment and inspections of the overall vehicle continue.
STS-87 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DM
NOTE: Hydraulic systems tests are in work through early next week. Removal of the liquid oxygen 17-inch disconnect is also in work. Water spray boiler check-outs began this morning.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/