STS-85 -- CRISTA-SPAS-2 (image)
NOTE: Discovery's payload bay doors are closed for the loading of hypergolic propellants aboard the Space Shuttle today. The pad is closed to all non-essential personnel for this operation which is expected to last through tomorrow.
Mission managers are meeting today at KSC for the Flight Readiness Review. Following this review, which concerns all aspects of the mission from launch to landing, a firm launch date is expected to be announced.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DMNOTE: The failed payload bay door hinge has been replaced and today tests involving the opening and closing of the doors are in work. The Mass Memory Unit No. 1 has been replaced and the thermal protection tiles for the forward reaction control system continue to be installed. The Shuttle's aft engine compartment and crew module close-outs continue in work. The final portion of the Crew Equipment Interface Test (CEIT) is scheduled for Saturday. A landing gear functional test is scheduled for next week. In the VAB, external tank/SRB mate activities are in work today.
STS-86 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-87 -- U.S. MICROGRAVITY PAYLOAD-4NOTE: Preparations to remove the MSL-1 Spacelab module continue in work. The laboratory will be removed on Monday and returned to the Operations and Checkout Building. The tunnel adapter is being removed today and a routine functional test of the forward reaction control system is scheduled for later this week.
STS-87 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DM
NOTE: Hydraulic systems servicing is complete to date as work to remove the liquid oxygen 17-inch disconnect continues. Preparations to install the Ku-band system antenna continue.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/