STS-94 -- Microgravity Science Laboratory-1 (image)
NOTE: Columbia's payload bay doors were closed for flight yesterday. Today, technicians are wrapping up close-out work in the orbiter's aft compartment and performing some tile work on nose of the vehicle. Preparations are in work for the orbiter's move to the Vehicle Assembly Building targeted for tomorrow at about 11 a.m. The external tank and solid rocket boosters await Columbia in VAB high bay 1 for a hard mate to be completed on Thursday. Once in the VAB, wiring work will continue in the Shuttle's avionics bay 4 and electrical check-outs of an auxiliary power unit will pick-up.
STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-85 -- CRISTA-SPAS-2 (image)
NOTE: Close-outs of Discovery's aft engine compartment continue. Work to secure engine No. 3 is now complete. Heat shield installation will begin next week and mid-body close-outs continue on schedule. Solid rocket booster stacking operations continue in the Vehicle Assembly Building.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DM
NOTE: Off-loading of hypergolic propellants from Atlantis' orbiter maneuvering system is complete. Preparations are underway for main engine removal currently scheduled for Thursday. The Spacehab module was removed from Atlantis' cargo bay yesterday and is currently located in KSC's Vertical Processing Facility where it will undergo post flight servicing and preparation for its next flight.
STS-86 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DMNOTE: Preparations are in work to move Endeavour from the VAB to OPF bay 1 tomorrow. Once Columbia arrives in the VAB for mating operations, Endeavour will be moved over and processing will begin for mission STS-89.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/