KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      FRIDAY, JUNE 6, 1997 (12:39 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: J.Wells-1@ksc.nasa.gov

      MISSION: STS-94 -- Microgravity Science Laboratory-1 (image)

      Index of STS-83/STS-94 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: Vehicle Assembly Building
      • TARGET KSC LAUNCH DATE/TIME: July 1 at 2:37 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: July 17 at 7:23 a.m.
      • MISSION DURATION: 15 days, 16 hours, 46 minutes
      • CREW: Halsell, Still, Voss, Gernhardt, Thomas, Crouch and Linteris (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees

      NOTE: Columbia is hard mated to the external fuel tank and solid rocket boosters and ordnance installation is in work. Preparations are in work for functional tests of the tail service mast. Rework on spliced wires in the Shuttle's avionics bay 4 will begin this weekend and electrical evaluations of a controller check-out unit for auxiliary power unit No. 2 will pick-up on Monday. Evaluations of the FRCS tiles on the other orbiters continue as managers seek to better understand the cracked tiles seen on Columbia last week.

      STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Shuttle interface test (June 9-10)
      • Roll out to pad 39A (June 11)
      • Flight Readiness Review (June 19)

      MISSION: STS-85 -- CRISTA-SPAS-2 (image)

      Index of STS-85 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: August 7 at 10:39 a.m.
      • LAUNCH WINDOW: 1 hour, 41 minutes
      • TARGET KSC LANDING DATE/TIME: August 18 at 7:27 a.m.
      • MISSION DURATION: 10 days, 20 hours, 48 minutes
      • CREW: Brown, Rominger, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: Heat shield installation is in work today. Mid-body close-outs continue on schedule. Inspections of the thermal protection tiles on the orbiter's forward reaction control system are in work. The external tank umbilical doors have been undergoing cycling tests for several weeks so engineers could study bent bolts on one door's hinge fixtures. Yesterday, stronger bolts were installed to prevent future bolt deformation. Solid rocket booster stacking operations continue in the VAB.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Crew equipment and interface test (June 14)

      MISSION: STS-86 -- 7th MIR DOCKING & SPACEHAB DM

      • VEHICLE: Atlantis/OV-104
      • LOCATION: Orbiter Processing Facility bay 3
      • TARGET KSC LAUNCH DATE/TIME: September 18 at about 1:39 a.m.
      • LAUNCH WINDOW: 10 minutes
      • TARGET KSC LANDING DATE/TIME: September 28 at 5:19 a.m.
      • MISSION DURATION: 10 days, 3 hours, 49 minutes
      • CREW: Wetherbee, Bloomfield, Parazynski, Titov, Chretien, Lawrence (up), Foale (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Atlantis' main engines were removed last night. Forward reaction control system trickle purge activities are complete. Inspections of the thermal protection tiles on the FRCS are also complete. Preparations are underway for removal and replacement of fuel cell No. 3, scheduled to begin on Monday. Spacehab tunnel inspections are also underway.


      MISSION: STS-89 -- 8th MIR DOCKING & SPACEHAB DM
      • VEHICLE: Endeavour/OV-105
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET KSC LAUNCH DATE/TIME: January 15, 1998 at about 12:57 a.m.
      • LAUNCH WINDOW: 7 - 10 minutes
      • TARGET KSC LANDING DATE/TIME: January 24, 1998 at about 5:20 a.m.
      • MISSION DURATION: 9 days, 4 hours, 23 minutes
      • CREW: Wilcutt, Edwards, Dunbar, Anderson, Reilly, Wolf (up), Lawrence (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Endeavour has been placed on jacks and leveled in OPF bay 1. Technicians are gaining access to the orbiter's payload bay with strong back installation complete. Processing work will now begin for Endeavour's next mission, STS-89.

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/