KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      FRIDAY, JUNE 20, 1997 (11:31 AM EDT)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: J.Wells-1@ksc.nasa.gov

      MISSION: STS-94 -- Microgravity Science Laboratory-1 (image)

      Index of STS-83/STS-94 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: Pad 39A (image)
      • TARGET KSC LAUNCH DATE/TIME: July 1 at 2:37 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: July 17 at 7:23 a.m.
      • MISSION DURATION: 15 days, 16 hours, 46 minutes
      • CREW: Halsell, Still, Voss, Gernhardt, Thomas, Crouch and Linteris (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees

      NOTE: Yesterday afternoon, following the STS-94 Flight Readiness Review, NASA managers announced July 1 as the official launch date for Columbia's reflight of the Microgravity Science Laboratory-1 mission.

      Loading of storable hypergolic propellants aboard Columbia continues through tonight. Tile installation work on the forward reaction control system is complete, with all 36 tiles bonded to the vehicle. Bond verification checks will begin after the loading of hypergolic propellants. In Columbia's aft compartment, work to install the fabricated "pyro can" assemblies at the orbiter's external tank attach points concludes Saturday.

      STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Ordnance installation (June 24)
      • Orbiter aft engine compartment close-outs (June 23)
      • Launch countdown begins (June 28)

      MISSION: STS-85 -- CRISTA-SPAS-2 (image)

      Index of STS-85 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: August 7 at 10:39 a.m.
      • LAUNCH WINDOW: 1 hour, 41 minutes
      • TARGET KSC LANDING DATE/TIME: August 18 at 7:27 a.m.
      • MISSION DURATION: 10 days, 20 hours, 48 minutes
      • CREW: Brown, Rominger, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: Integrated hydraulic testing continues. Potable water servicing and thermal protection system (TPS) waterproofing are both in work today. Fit checks for the TPS tiles on Discovery's forward reaction control system continue and tile installation is being worked concurrently. Preparations are in work for payload bay door closure scheduled to occur next week. In the Vehicle Assembly Building, work is underway to mate the external tank to the solid rocket boosters.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Close payload bay doors (June 24)
      • Orbiter roll to VAB for mate to ET/SRB stack (July 7)

      MISSION: STS-86 -- 7th MIR DOCKING & SPACEHAB DM

      • VEHICLE: Atlantis/OV-104
      • LOCATION: Orbiter Processing Facility bay 3
      • TARGET KSC LAUNCH DATE/TIME: September 18 at about 1:39 a.m.
      • LAUNCH WINDOW: 10 minutes
      • TARGET KSC LANDING DATE/TIME: September 28 at 5:19 a.m.
      • MISSION DURATION: 10 days, 3 hours, 49 minutes
      • CREW: Wetherbee, Bloomfield, Parazynski, Titov, Chretien, Lawrence (up), Foale (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: The orbital maneuvering system pod functional checks continue through Monday. Window No. 1 is installed and polishing of Atlantis' other windows will continue through Monday. Radiator functional testing is in work.


      MISSION: STS-89 -- 8th MIR DOCKING & SPACEHAB DM
      • VEHICLE: Endeavour/OV-105
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET KSC LAUNCH DATE/TIME: January 15, 1998 at about 12:57 a.m.
      • LAUNCH WINDOW: 7 - 10 minutes
      • TARGET KSC LANDING DATE/TIME: January 24, 1998 at about 5:20 a.m.
      • MISSION DURATION: 9 days, 4 hours, 23 minutes
      • CREW: Wilcutt, Edwards, Dunbar, Anderson, Reilly, Wolf (up), Lawrence (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Preparations are in work for servicing of freon coolant loop No. 2. Radiator functional tests are scheduled for next week. Testing of Discovery's atmospheric revitalization pressure control system is underway.

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT

      GO TO THE STATUS REPORTS HOME PAGE