STS-94 -- Microgravity Science Laboratory-1 (image)
NOTE: Loading of storable hypergolic propellants aboard Columbia was completed Friday night. Over the weekend, workers finished bond verification on the 36 thermal protection tiles that were installed on the nose of the orbiter. In Columbia's aft compartment, work to install the fabricated "pyro can" assemblies at the orbiter's external tank attach points continues.
STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-85 -- CRISTA-SPAS-2 (image)
NOTE: Integrated hydraulic testing continues. Potable water servicing continues in work through today. Six of the 44 forward reaction control system tiles slated for replacement on Discovery are installed and bonded, and work continues to fit check and install the remaining tiles. Close-outs of Discovery's aft compartment continue this week. Preparations are underway for payload bay door closure set to occur tomorrow. In the Vehicle Assembly Building, work to mate the external tank to the solid rocket boosters is complete.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DM
NOTE: Atlantis' orbital maneuvering system pod functional checks continue through tomorrow. Auxiliary power unit leak and functional checks are complete and main propulsion system leak and functional checks are in work. Testing of the power reactant storage and distribution system is underway. Fabrication of the replacement tiles for Atlantis' forward reaction control system is in work and installation will begin next week. Window polishing continues through Friday.
STS-89 -- 8th MIR DOCKING & SPACEHAB DMNOTE: Work to replace a faulty flow transducer in Endeavour's freon coolant loop No. 2 is underway and servicing of that coolant loop will begin later this week. Radiator functional tests are in work this week.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/