STS-94 -- Microgravity Science Laboratory-1 (image)
NOTE: At the launch pad, solid rocket booster close-outs are complete and work to close-out Columbia's aft compartment will conclude today. Launch countdown preparations continue with liquid hydrogen and oxygen system conditioning complete. Payload revitalization and battery charging are in work.
STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-85 -- CRISTA-SPAS-2 (image)
NOTE: Tile replacement work continues on Discovery's forward reaction control system. Close-outs of Discovery's aft compartment continue through Saturday and aft structural leak checks are in work. In the Vehicle Assembly Building, external tank and solid rocket booster close-outs continue.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DM
NOTE: Inspections of the main propulsion system 17-inch disconnects are in work today. Testing of Atlantis' power reactant storage and distribution system is in work. Troubleshooting is underway on a startracker that had a brief data drop-out during testing. Fabrication of the replacement tiles for Atlantis' forward reaction control system is in work and installation will begin next week. Window polishing continues.
STS-89 -- 8th MIR DOCKING & SPACEHAB DMNOTE: Servicing of Endeavour's freon coolant loop No. 2 and radiator functional tests will continue next week. Weight-saving modifications on the left and right hand elevon coves, where the back of the orbiter's wings meet the elevons, are in work through Monday. Engineers are evaluating leak check data from a 17-inch disconnect on the umbilical assembly that joins the external tank to the orbiter.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/