KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
THURSDAY, MARCH 6, 1997 (10:43 AM EST)
KSC Public Affairs Contact: Bruce Buckingham (fax 407-867-2692)
E-mail: Bruce.Buckingham-1@kmail.ksc.nasa.gov
MISSION:
STS-83 -- Microgravity Science Laboratory-1
- VEHICLE: Columbia/OV-102
- LOCATION: Vehicle Assembly Building
- TARGET LAUNCH DATE/TIME: April 3 at 2:01 p.m. EST
- LAUNCH WINDOW: 2 hours, 30 minutes
- TARGET KSC LANDING DATE/TIME: April 19 at about 7:37 a.m. EDT
- MISSION DURATION: 15 days, 16 hours, 36 minutes
- CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees
NOTE: Columbia was moved to the Vehicle Assembly Building yesterday with
first motion from OPF Bay 1 occurring at about 1 p.m. Overnight,
Columbia was lifted to the vertical position and mated to the external
tank and solid rocket boosters. Hard mate is expected to be complete by
early afternoon today. The Shuttle interface test will begin this
weekend and roll out to Pad 39A is scheduled for Monday, March 10.
- STS-83 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Begin Shuttle interface test (Saturday)
- * Roll out to Pad 39A (first motion set for 7 a.m. March 10)
- * Hot fire auxiliary power unit No. 2 (March 10)
- * Terminal Countdown Demonstration Test (TCDT) (March 13-14)
- * Remove and replace SRB nozzle plugs (March 15)
MISSION:
STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
- VEHICLE: Atlantis/OV-104
- LOCATION: Orbiter Processing Facility bay 3
- TARGET KSC LAUNCH DATE/TIME: May 15 at about 4:07 a.m.
- LAUNCH WINDOW: 7-10 minutes
- TARGET KSC LANDING DATE/TIME: May 24 at about 7:52 a.m.
- MISSION DURATION: 9 days, 3 hours, 45 minutes
- CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees
NOTE: Electrical connections between the forward reaction control system
and the orbiter are complete. Today, the Space Shuttle main engines are
being installed. Engine No. 1 will be installed by this afternoon,
followed by engine No. 3 tonight and engine No. 2 early tomorrow
morning. Mid-body close-outs also continue in work today.
- STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Complete installation of Space Shuttle main engines (Friday)
- * Orbiter Docking System functional check (March 13-14)
- * Mate external tank to solid rocket boosters (March 24)
- * Roll over to the VAB (April 9)
MISSION:
STS-85 -- CRISTA-SPAS-2
- VEHICLE: Discovery/OV-103
- LOCATION: Orbiter Processing Facility bay 2
- TARGET LAUNCH DATE/TIME: July 17 at 10:06 a.m.
- LAUNCH WINDOW: 1 hour, 54 minutes
- TARGET KSC LANDING DATE/TIME: July 28 at about 6:54 a.m.
- MISSION DURATION: 10 days, 20 hours, 48 minutes
- CREW: Brown, Ashby, Davis, Curbeam, Robinson, Tryggvason
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees
NOTE: Deservicing of the hypergolic system is complete and the bay has
been reopened for routine work. The orbiter navigational aid activation
test has been rescheduled for next week. Today, the main landing gear
wheel and tire assembly will be removed and the brakes inspected.
- STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Fuel cell voltage tests (March 14)
- * Remove Space Shuttle main engines (March 28)
--end--
For automatic e-mail subscriptions to this daily Shuttle
status report or KSC originated press releases, send an Internet
electronic mail message to domo@news.ksc.nasa.gov. In the body of the
message (not the subject line) type the words "subscribe
shuttle-status", or "subscribe ksc-press-release" (do not use
quotation marks). The system will reply with a confirmation via
e-mail of each subscription.
To remove your name from the list at any time, send an e-mail
address to domo@news.ksc.nasa.gov. In the body of the message (not
the subject line), type (no quotes) "unsubscribe shuttle-status", or
"unsubscribe ksc-press-release."
Status reports and other NASA publications are available on