KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
FRIDAY, MARCH 14, 1997 (11:30 AM EST)
KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
E-mail: J.Wells-1@kmail.ksc.nasa.gov
MISSION:
STS-83 -- Microgravity Science Laboratory-1
- VEHICLE: Columbia/OV-102 (image)
- LOCATION: Pad 39A
- TARGET LAUNCH DATE/TIME: April 3 at 2:01 p.m. EST
- LAUNCH WINDOW: 2 hours, 30 minutes
- TARGET KSC LANDING DATE/TIME: April 19 at about 7:37 a.m. EDT
- MISSION DURATION: 15 days, 16 hours, 36 minutes
- CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees
NOTE: The STS-83 Terminal Countdown Demonstration Test (TCDT) continues with
a mock launch countdown culminating in a simulated main engine cutoff at 11
a.m. today.
Preparations to replace a low pressure fuel turbo pump on
main engine No. 1
are complete and the spare pump is ready for installation. Due to high winds
last night, the fuel pump replacement will be worked in tandem with SRB
nozzle plug work through the weekend.
- STS-83 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Terminal Countdown Demonstration Test (TCDT) (today)
- * Remove and replace the low pressure fuel turbo pump on SSME No. 1
(weekend)
- * Remove and replace SRB nozzle plugs (weekend)
- * Flight Readiness Review (March 20)
- * Ordnance installation (March 26)
MISSION:
STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
- VEHICLE: Atlantis/OV-104
- LOCATION: Orbiter Processing Facility bay 3
- TARGET KSC LAUNCH DATE/TIME: May 15 at about 4:07 a.m.
- LAUNCH WINDOW: 7-10 minutes
- TARGET KSC LANDING DATE/TIME: May 24 at about 7:52 a.m.
- MISSION DURATION: 9 days, 3 hours, 45 minutes
- CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees
NOTE: Orbiter Docking System functional checks continue today and should be
complete tonight. Borescope inspections of Atlantis' three main engines are
complete and no fuel pump anomolies were found.
- STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Orbiter Docking System functional check (today)
- * Remove and replace SRB nozzle plugs in the VAB (March 19-20)
- * Crew equipment and interface test (March 22)
- * Mate external tank to solid rocket boosters (March 24)
- * Close payload bay doors for roll to VAB (March 31)
- * Roll over to the VAB (April 9)
MISSION:
STS-85 -- CRISTA-SPAS-2
- VEHICLE: Discovery/OV-103
- LOCATION: Orbiter Processing Facility bay 2
- TARGET LAUNCH DATE/TIME: July 17 at 10:06 a.m.
- LAUNCH WINDOW: 1 hour, 54 minutes
- TARGET KSC LANDING DATE/TIME: July 28 at about 6:54 a.m.
- MISSION DURATION: 10 days, 20 hours, 48 minutes
- CREW: Brown, Ashby, Davis, Curbeam, Robinson, Tryggvason
- ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees
NOTE: Check-outs of the orbital maneuvering system and reaction control
system continue. Preparations for Space Shuttle main engine removal also
continue. Hydraulic system inspection is in work today.
- STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
- * Fuel cell voltage tests (today)
- * Forward reaction control system functional checks (March 21)
- * Remove Space Shuttle main engines (March 28)
--end--
For automatic e-mail subscriptions to this daily Shuttle
status report or KSC originated press releases, send an Internet
electronic mail message to domo@news.ksc.nasa.gov. In the body of the
message (not the subject line) type the words "subscribe
shuttle-status", or "subscribe ksc-press-release" (do not use
quotation marks). The system will reply with a confirmation via
e-mail of each subscription.
To remove your name from the list at any time, send an e-mail
address to domo@news.ksc.nasa.gov. In the body of the message (not
the subject line), type (no quotes) "unsubscribe shuttle-status", or
"unsubscribe ksc-press-release."
Status reports and other NASA publications are available on
the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed
electronically via the Internet at:
http://www.ksc.nasa.gov/shuttle/countdown/ and at
http://shuttle.nasa.gov/