KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      THURSDAY, MAY 1, 1997 (2:19 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: J.Wells-1@ksc.nasa.gov

      MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
      • VEHICLE: Atlantis/OV-104
      • LOCATION: Pad 39A (image)
      • TARGET KSC LAUNCH DATE/TIME: May 15 at 4:08 a.m.
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: May 24 at 7:49 a.m.
      • MISSION DURATION: 9 days, 3 hours, 41 minutes
      • CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Following yesterday's Flight Readiness Review, Shuttle managers announced May 15 as the official launch date of Atlantis on mission STS-84. Today, Pad 39A remains closed to all but necessary personnel in support of hypergolic propellant loading activities. Oxidizer loading is complete and fuel loading will continue through tonight. The pad will reopen on Friday morning for normal work.

      Preparations are in work to mate the transfer tunnel to the crew compartment and the Spacehab module. The payload bay doors will be opened tomorrow. Tunnel leak checks are slated for tomorrow and cabin leak checks will occur over the weekend. Solid rocket booster close-outs are in work.

      STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Prelaunch propellant load complete (tonight)
      • Tunnel leak checks (May 2)
      • Payload interface verification test (May 5)
      • Orbiter aft compartment close-outs complete (May 9)
      • Payload bay doors closed for flight (May 9)

      MISSION: STS-94 -- Microgravity Science Laboratory-1 (image)
      • VEHICLE: Columbia/OV-102 (image)
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET LAUNCH DATE/TIME: July 1 at 2:37 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: July 17 at 7:23 a.m.
      • MISSION DURATION: 15 days, 16 hours, 46 minutes
      • CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees

      NOTE: Orbiter maneuvering system pod functional checks and main propulsion system leak and functional checks are in work through Friday. Work on the forward reaction control system continues in preparation for delivery to the OPF on Monday. Spacelab reservicing activities continue and experiment testing will be in work over the next two weeks.

      STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Forward reaction control system installation (May 6)
      • Space Shuttle main engine installation (May 7)
      • Spacelab/orbiter interface verification test (May 7 and 8)

      MISSION: STS-85 -- CRISTA-SPAS-2
      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET LAUNCH DATE/TIME: August 7 at 10:39 a.m.
      • LAUNCH WINDOW: 1 hour, 41 minutes
      • TARGET KSC LANDING DATE/TIME: August 18 at 7:27 a.m.
      • MISSION DURATION: 10 days, 20 hours, 48 minutes
      • CREW: Brown, Rominger, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: Forward reaction control system interface verification tests continue through tomorrow. Inspections and close-outs in Discovery's midbody continue. Next week technicians will cycle Discovery's external tank doors to check out the power drive units. Payload premate activities are in work through next week.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Space Shuttle main engine installed (May 12 and 13)

      MISSION: STS-88 -- FIRST ISS ASSEMBLY FLIGHT

      ENDEAVOUR (OV-105) NOTE: Endeavour is located in Orbiter Processing Facility bay 3. Removal of orbiter maneuvering system pod simulators is in work through Friday. Windows No. 1 and No. 6 are slated for removal and replacement.

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/