KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      TUESDAY, MAY 6, 1997 (1:34 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: J.Wells-1@ksc.nasa.gov

      MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
      • VEHICLE: Atlantis/OV-104
      • LOCATION: Pad 39A (image)
      • TARGET KSC LAUNCH DATE/TIME: May 15 at about 4:08 a.m.
      • LAUNCH WINDOW: 7 minutes
      • TARGET DOCKING WITH MIR: May 16 at about 10:38 p.m.
      • TARGET UNDOCKING WITH MIR: May 21 at about 9:04 p.m.
      • TARGET KSC LANDING DATE/TIME: May 24 at 7:49 a.m.
      • MISSION DURATION: 9 days, 3 hours, 41 minutes
      • CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Main propulsion system purge activities are complete. Preparations are in work for ordinance installation tonight and countdown preparations are also underway. Close-out activities continue in Atlantis' aft compartment. At the pad yesterday, a work stand contacted a battery cable that provides power to an accelerometer on the right SRB. A technician noted electrical arcing between the platform and the cable. The cable has been changed out and work to replace the battery is scheduled for today. The payload interface verification test continues through tonight.

      STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Orbiter aft compartment close-outs complete (May 9)
      • Payload bay doors closed for flight (May 9)
      • Launch countdown begins (May 11)
      • STS-84 crew arrival (May 11)

      MISSION: STS-94 -- Microgravity Science Laboratory-1 (image)
      • VEHICLE: Columbia/OV-102 (image)
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET LAUNCH DATE/TIME: July 1 at 2:37 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: July 17 at 7:23 a.m.
      • MISSION DURATION: 15 days, 16 hours, 46 minutes
      • CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees

      NOTE: Due to extended work on Columbia's body flap, Space Shuttle main engine installation is now slated for Friday and Saturday. Fuel cell voltage tests are complete. Installation of auxiliary power unit No. 3 is in work and preparations are under way for installation of auxiliary power unit No. 2. The forward reaction control system is slated for installation this weekend. In the VAB, preparations are underway for next week's planned external tank/solid rocket booster mating activities. Spacelab reservicing is wrapping up today and experiment testing will begin tomorrow.

      STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Spacelab/orbiter interface verification test (May 7 and 8)
      • Space Shuttle main engine installation (May 9 and 10)
      • Forward reaction control system installation (May 10)

      MISSION: STS-85 -- CRISTA-SPAS-2
      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET LAUNCH DATE/TIME: August 7 at 10:39 a.m.
      • LAUNCH WINDOW: 1 hour, 41 minutes
      • TARGET KSC LANDING DATE/TIME: August 18 at 7:27 a.m.
      • MISSION DURATION: 10 days, 20 hours, 48 minutes
      • CREW: Brown, Rominger, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: Cycling of Discovery's external tank doors is in progress today. Work continues on the orbiter's body flap and main engine installation begins early next week. Payload premate activities continue through tomorrow and midbody close-outs are in work.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Space Shuttle main engine installation (May 12 and 13)

      MISSION: STS-88 -- ISS-01-2A

      ENDEAVOUR (OV-105) NOTE: Endeavour is located in Orbiter Processing Facility bay 3. Validation of the orbiter's electrical system is complete for this week, but will pickup again next week. Orbiter coolant loop servicing continues. Removal of the right hand orbiter maneuvering system simulator is in work through Wednesday.

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/