KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      THURSDAY, MAY 8, 1997 (12:34 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: J.Wells-1@ksc.nasa.gov

      MISSION: STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)
      • VEHICLE: Atlantis/OV-104
      • LOCATION: Pad 39A (image)
      • TARGET KSC LAUNCH DATE/TIME: May 15 at about 4:08 a.m.
      • LAUNCH WINDOW: 7 minutes
      • TARGET DOCKING WITH MIR: May 16 at about 10:39 p.m.
      • TARGET UNDOCKING WITH MIR: May 21 at about 9:05 p.m.
      • TARGET KSC LANDING DATE/TIME: May 24 at 7:53 a.m.
      • MISSION DURATION: 9 days, 3 hours, 45 minutes
      • CREW: Precourt, Collins, Foale, Noriega, Lu, Clervoy, Kondakova (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Close-out activities continue in Atlantis' aft compartment. The engine compartment doors are scheduled for installation tomorrow. Hypergolic propellant pressurization is complete. Testing of the orbiter's global positioning and inertial navigation systems continues today. Payload vertical close-outs are in work and payload bay door closure is slated for about 8 p.m. tomorrow.

      STS-84 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Orbiter aft compartment close-outs complete (May 9)
      • Payload bay doors closed for flight (May 9)
      • Launch countdown begins (May 11 at 11 p.m.)
      • STS-84 crew arrival (May 11 at 10:30 p.m.)

      MISSION: STS-94 -- Microgravity Science Laboratory-1 (image)
      • VEHICLE: Columbia/OV-102 (image)
      • LOCATION: Orbiter Processing Facility bay 1
      • TARGET LAUNCH DATE/TIME: July 1 at 2:37 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: July 17 at 7:23 a.m.
      • MISSION DURATION: 15 days, 16 hours, 46 minutes
      • CREW: Halsell, Still, Voss, Thomas, Gernhardt, Linteris, Crouch (image)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/28.45 degrees

      NOTE: Work to install auxiliary power units No. 2 and No. 3 continues. The forward reaction control system arrived in the OPF last night and will be installed into the orbiter this weekend. Main engine installation is scheduled to begin Friday morning. The Spacelab interface verification test is in work and experiment health checks are scheduled through Friday night. In the VAB, preparations are underway for next week's planned external tank/solid rocket booster mating activities.

      STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Space Shuttle main engine installation (May 9 and 10)
      • Forward reaction control system installation (May 10)

      MISSION: STS-85 -- CRISTA-SPAS-2
      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET LAUNCH DATE/TIME: August 7 at 10:39 a.m.
      • LAUNCH WINDOW: 1 hour, 41 minutes
      • TARGET KSC LANDING DATE/TIME: August 18 at 7:27 a.m.
      • MISSION DURATION: 10 days, 20 hours, 48 minutes
      • CREW: Brown, Rominger, Davis, Curbeam, Robinson, Tryggvason
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/57 degrees

      NOTE: Preparations are in work for main engine installation on Monday. Payload premate activities continue. Engineering continues to analyze data on the bent bolts in the linkage of the power drive unit on the right hand external tank door.

      STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Space Shuttle main engine installation (May 12 and 13)
      • Payload installation (May 14)

      MISSION: STS-88 -- ISS-01-2A

      ENDEAVOUR (OV-105) NOTE: Endeavour is located in Orbiter Processing Facility bay 3. The freon coolant loop over pressurization test is complete and good. Removal of the right hand orbiter maneuvering system simulator is complete. Orbiter maneuvering system/reaction control system wiring work is in progress.

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      GO TO THE PREVIOUS SPACE SHUTTLE STATUS REPORT
      GO TO THE NEXT SPACE SHUTTLE STATUS REPORT

      GO TO THE STATUS REPORTS HOME PAGE