STS-84 -- 6th MIR DOCKING & SPACEHAB DM (image)NOTE: Postlaunch inspections at pad 39A revealed only minor damage and the mobile launch platform is scheduled to roll off the pad surface next week.
The solid rocket booster retrieval ships began recovery operations at about 6 a.m. yesterday and are expected to return to Hangar AF with boosters in tow today at 1:30 p.m. and 3:30 p.m.
The crew of STS-84 are: Commander Charles Precourt, Pilot Eileen Collins and Mission Specialists Jean-Francois Clervoy, Carlos Noriega, Edward Lu, Elena Kondakova, Michael Foale (up) and Jerry Linenger (down). (image)
STS-94 -- Microgravity Science Laboratory-1 (image)
NOTE: Main engine installation and securing were completed this week and forward reaction control system external close-outs are in work. Ammonia servicing preparations are underway. Columbia's nose landing gear is closed for tile work and heat shield installation will pickup tomorrow. Work to connect auxiliary power unit fuel lines is scheduled for Monday and Tuesday. Evaluations of Columbia's fuel cell performance monitors are in work.
The forward extension of the tunnel adapter is being installed today. During Spacelab health checks earlier this week, payload technicians identified a error message on a mass memory unit and work to remove and replace that MMU is complete. In the VAB, external tank/SRB mating operations were completed on Tuesday.
STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-85 -- CRISTA-SPAS-2 (image)
NOTE: Main engine installation is complete and securing is in work. The Manipulator Flight Demonstration payload was installed on Wednesday and the interface verification test is scheduled for Monday. Get Away Special payload installation is in work.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 -- ISS-01-2AENDEAVOUR (OV-105) NOTE: Endeavour is located in Orbiter Processing Facility bay 3. Servicing of freon coolant loop No. 1 was completed on Wednesday. The main propulsion system gaseous hydrogen blowdown is complete. Preparations are underway to roll Endeavour to the Vehicle Assembly Building next week to make room in the OPF for Atlantis, once it lands at KSC on Saturday.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/