STS-94 -- Microgravity Science Laboratory-1 (image)
NOTE: Mid-body close-outs continue on Columbia as work proceeds to install the spacelab transfer tunnel on Thursday. Work to remove and replace the cracked fuse holders on the orbiter's power distribution assembly is complete and retests were good. Roll to the VAB is currently targeted for late in the evening of June 4.
STS-94 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-85 -- CRISTA-SPAS-2 (image)
NOTE: External tank door tests continue today. Work to replace a joint seal on main engine No. 3 will begin once the engine is removed from the engine compartment today. Mid-body close-outs remain on schedule. Solid rocket booster stacking operations continue in the Vehicle Assembly Building.
STS-85 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-86 -- 7th MIR DOCKING & SPACEHAB DM
NOTE: Post-flight assessments continue today. The payload bay doors are scheduled to be opened today at about noon and the Spacehab will be removed on Friday. Post flight inspections of the forward reaction control system are complete and orbiter maneuvering system/reaction control system trickle purge activation is complete as well.
STS-86 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DMNOTE: Endeavour will remain in temporary storage in the VAB until Columbia is rolled out of OPF bay No. 3 and to the VAB for mating operations. Once the OPF is open, Endeavour will be moved over and processing will begin for its newly assigned flight, STS-89.
STS-89 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/