STS-87 -- U.S. MICROGRAVITY PAYLOAD-4
NOTE: Post-Terminal Countdown Demonstration Test securing and crew module destow activities on Columbia are complete. The pad will be closed today and tomorrow for loading of hypergolic propellants into the orbiter.
STS-87 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DM
NOTE: Integrated hydraulic operations are complete and close-outs of Endeavour's air lock continue through Saturday. The orbiter's fuel cell monitoring modifications continue with performance monitor connections complete. Main propulsion system electrical close-outs continue with resistance checks today. Orbiter maneuvering system tests are also underway. Payload premate testing continues and transfer-tunnel installation is slated for early next week.
STS-89 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9th MIR DOCKING & SPACEHAB-SMNOTE: Work to purge Discovery's reaction control system is complete and hydraulic testing is underway. Technicians are removing thermal protective tiles from the area beneath the orbiter's nose in preparation for "chin panel" modifications. Fuel cell monitoring modifications continue.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
NOTE: Preparations for Atlantis' ferry flight to Palmdale, CA, continue on schedule. Aft compartment close-outs are slated for tonight. Mating of the orbiter to the top of the Shuttle Carrier Aircraft (SCA) is set for Nov. 10 and departure for Palmdale is planned for early Nov. 11. The SCA is scheduled to arrive at the Shuttle Landing Facility tomorrow afternoon.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/