STS-86 -- 7th MIR DOCKING & SPACEHAB DM
NOTE: At Hangar AF, solid rocket booster aft skirt assembly removal is complete and forward skirt removal is in work. The booster nozzles will also be removed today for shipment to Utah tomorrow.
Atlantis continues to perform very well on orbit with most of the Mir transfer activities complete.
STS-87 -- U.S. MICROGRAVITY PAYLOAD-4
NOTE: Today the STS-87 crew arrived at KSC to participate in mission familiarization activities. Tomorrow they will take part in the Crew Equipment Interface Test in Columbia's crew module and midbody. Integrated testing of the main propulsion system continues. A faulty connector on the fuel cell monitoring system in the orbiter's midbody will be changed out and retested this week. Fuel cell voltage tests and payload premate testing are slated for next week.
STS-87 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-89 -- 8th MIR DOCKING & SPACEHAB DM
NOTE: Leak and functional checks of Endeavour's three auxiliary power units will conclude tomorrow. Main propulsion system testing is underway. The orbiter's forward reaction control system arrived in the OPF at 10:30 a.m. today and following inspections will be installed into the orbiter tonight. In the Hypergolic Maintenance Facility, work continues on the right hand orbital maneuvering system (OMS) pod in preparation for its delivery to the OPF tomorrow.
STS-89 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9th MIR DOCKING & SPACEHAB-SMNOTE: Yesterday at about 1:30 p.m. Discovery arrived in VAB high bay 2 to make room in OPF bay 3 for Atlantis' return. Portable purge systems have been hooked-up and the orbiter will remain in temporary storage until Oct. 27.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/