KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      WEDNESDAY, APRIL 1, 1998 (2:06 PM EST)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: Joel.Wells-1@ksc.nasa.gov

      Launch Viewing Information


      MISSION: STS-90 -- NEUROLAB

      STS-90 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: Pad 39B
      • TARGET KSC LAUNCH DATE/TIME: April 16, 1998 at 2:19 p.m. EDT
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • *TARGET KSC LANDING DATE/TIME: May 3 at 11:07 a.m. EDT
      • *EXPECTED MISSION DURATION: 16 days, 21 hours, 48 minutes
      • CREW: Searfoss, Altman, Linnehan, Williams, Hire, Buckey, Pawelczyk
      • ORBITAL ALTITUDE and INCLINATION: 150 nautical miles/39 degrees
        *The mission is currently baselined to last 16 days (MET of 15/21:50). The option to add the 17th day, (MET of 16/21:48) if power margins permit, will be addressed during the flight.

      NOTE: Yesterday, the Terminal Countdown Demonstration Test was completed successfully. Loading of prelaunch propellants into Columbia's on-board storage tanks begins today and continues through Friday. Drying of the gaseous nitrogen (GN2) lines on the mobile launch platform is in progress as GN2 system cleaning efforts conclude. Technicians will resume external tank ordnance canister modifications in Columbia's aft compartment after hypergolic loading is complete. Early next week, orbiter aft compartment close-outs and ordnance installation will begin.

      STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Flight Readiness Review (April 2)
      • Orbiter aft compartment closeouts begin (April 6)
      • Ordance installation (April 7)
      • Launch countdown begins (April 13 at 2 a.m.)

      MISSION: STS-91 -- 9TH AND FINAL MIR DOCKING, SPACEHAB-SM

      STS-91 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: OPF bay 2
      • TARGET KSC LAUNCH DATE/TIME: May 28 at 8:05 p.m. EDT
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: June 7 at about 3:36 p.m. EDT
      • MISSION DURATION: 9 days, 18 hours, 31 minutes
      • CREW: Precourt, Gorie, Lawrence, Chang-Diaz, Kavandi, Ryumin, Thomas (down)
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Functional tests of Discovery's external tank umbilical doors and ammonia system servicing are complete. Technicians have also completed installation of the payload bay camera. Heat shield and body flap work continues in the orbiter's aft compartment as preparations for main engine installation are in work. Payload premate testing will conclude today and preparations for tunnel adapter installation continue. In the Vehicle Assembly Building high bay 1, external tank and solid rocket booster mating activities resume today following super lightweight tank weighing operations.

      STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • ET/SRB mate (April 1)
      • Shuttle main engine installation begins (April 2)
      • Crew Equipment Interface Test (April 4)

      MISSION: STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION
      (NODE-1, PMAs 1 and 2)

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: July 9, 1998, at 12:44 p.m. EDT (under review)
      • LAUNCH WINDOW: 10 minutes
      • TARGET KSC LANDING DATE/TIME: July 20, 1998 at 8:02 a.m. EDT
      • MISSION DURATION: 10 days, 19 hours, 18 minutes
      • CREW: Cabana, Sturckow, Currie, Ross, Newman
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Draining of Endeavour's right-hand orbiter maneuvering system fuel cross-feed lines is complete and removal of any residual fuel is in work. Torque checks of the right wing-to-fuselage attach bolts continue. Removal of the orbiter's forward reaction control system (FRCS) is in work and the FRCS will be delivered to the Hypergol Maintenance Facility tomorrow to undergo thruster replacement. Main propulsion system gaseous hydrogen leak checks are slated to occur this week.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Remove right-hand orbital maneuvering system pod (April 2)
      • Forward reaction control system removal (April 8)
      • Remote manipulator system installed (April 9)

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/