![]() THURSDAY, APRIL 2, 1998 (11:16 AM EST) E-mail: Joel.Wells-1@ksc.nasa.gov STS-90 -- NEUROLAB
NOTE: At Pad 39B, launch preparations continue on schedule. Prelaunch oxidizer loading is complete and loading of fuel into Columbia's on-board storage tanks is in work. Cleaning of the gaseous nitrogen lines on the mobile launch platform continues through tomorrow. Today, workers will run cycling tests on the circuit breaker controller that supports Columbia's main engine No. 2. Technicians will resume external tank ordnance canister modifications in Columbia's aft compartment after hypergolic loading is complete. Early next week, orbiter aft compartment close-outs and ordnance installation will begin. The STS-90 Flight Readiness Review is under way and NASA managers are expected to announce April 16 as Columbia's official launch date at the conclusion of the meeting. STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH AND FINAL MIR DOCKING, SPACEHAB-SM
NOTE: Workers are removing access platforms used for Discovery's body flap work to make way for Shuttle main engine installation efforts. Engine installation is slated to begin late tonight and body flap rub panel work will resume next week. Payload premate testing has resumed today following successful troubleshooting of a failed signal during yesterday's testing. Tunnel adapter installation is slated to begin early next week. In Vehicle Assembly Building high bay 1, mating of the first super lightweight external tank and STS-91 solid rocket boosters is complete. STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION(NODE-1, PMAs 1 and 2)
NOTE: Removal of Endeavour's forward reaction control system (FRCS) was completed yesterday, and the FRCS will be moved to the Hypergol Maintenance Facility today for about one month of work to replace a leaky thruster. Removal of residual fuel from the orbiter's right-hand OMS cross-feed lines continues in preparation for next week's removal of the right-hand OMS pod. Torque checks of the right wing-to-fuselage attach bolts continue. Main propulsion system gaseous hydrogen leak checks are slated for this week. STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release." Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/ |