KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      MONDAY, AUGUST 10, 1998 (12:18 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax: 407-867-2692)

      Launch Viewing Information

      MISSION: STS-95 -- SPACEHAB-SM, SPARTAN & HOST

      STS-95 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: Oct. 29 at 2 p.m. EST
      • TARGET KSC LANDING DATE/TIME: Nov. 7 at 12:04 p.m. EST
      • MISSION DURATION: 8 days, 22 hours and 4 minutes
      • CREW: Brown, Lindsey, Parazynski, Robinson, Duque, Makai, Glenn
      • ORBITAL ALTITUDE and INCLINATION: 310 nautical miles/28.45 degrees

      NOTE: Electrical tests on Discovery's orbiter maneuvering system and auxiliary power unit leak and functional tests are complete. Integrated hydraulic tests begin today. Water spray boiler servicing is in work and gaseous nitrogen servicing of the orbiter's life support system is under way. Installation of the integrated vehicle health monitoring system continues and heat shield rework is nearing completion.

      STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Shuttle main engine installation (Aug. 18)
      • Crew Equipment Interface Test (Aug. 27)

      MISSION: STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION
      UNITY connecting module

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 at 4:45 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Dec. 14 at 12:45 a.m. EST
      • MISSION DURATION: 10 days, 20 hours
      • CREW: Cabana, Sturckow, Currie, Ross, Newman, Krikalev
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Electrical testing of Endeavour's orbiter docking system is complete. Main engine heat shield attach point rework continues. Power converter units No. 1 and No. 2 are being installed today. Tunnel adapter installation begins next Wednesday.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Transfer tunnel adapter installation (Aug. 19)
      • Shuttle main engine installation (Aug. 24)

      MISSION: STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: Jan. 21, 1999 at 11:37 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Jan. 26, 1999 at 10:40 a.m. EST
      • LAUNCH WINDOW: 43 minutes
      • MISSION DURATION: 4 days, 23 hours, 3 minutes
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Columbia's power control assembly No. 1 and digital command assembly No. 1 have been replaced. Technicians are troubleshooting a leaky waste tank valve on board the orbiter. The STS-93 super lightweight external fuel tank arrives at KSC from its manufacturing facility in New Orleans this week.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/