KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      THURSDAY, AUGUST 27, 1998 (3:44 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax: 407-867-2692)

      Launch Viewing Information

      MISSION: STS-95 -- SPACEHAB-SM, SPARTAN & HOST

      STS-95 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: Oct. 29 at 2 p.m. EST
      • TARGET KSC LANDING DATE/TIME: Nov. 7 at 12:04 p.m. EST
      • MISSION DURATION: 8 days, 22 hours and 4 minutes
      • CREW: Brown, Lindsey, Parazynski, Robinson, Duque, Makai, Glenn
      • ORBITAL ALTITUDE and INCLINATION: 310 nautical miles/28.45 degrees

      NOTE: Securing Discovery's main engines and main propulsion system leak and functional tests are complete. Potable water servicing is in progress and preparations for tunnel adapter installation have resumed. Today, technicians are installing the main engine heat shields and proceeding with integrated vehicle health monitoring hardware installation in the aft and midbody compartments. This afternoon the Ku-band antenna will be deployed and undergo electronic retests. In high bay 1 of the Vehicle Assembly Building, mating of the external tank and solid rocket boosters was completed Tuesday.

      STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Tunnel adapter installation complete (Aug. 28)
      • Payload premate test (Aug. 28)
      • Crew Equipment Interface Test (Sept. 2)
      • Payload bay door closure (Sept. 8)
      • Orbiter roll over to VAB (Sept. 14)

      MISSION: STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION
      UNITY connecting module

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 at 4:45 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Dec. 14 at 11:14 p.m. EST
      • MISSION DURATION: 11 days, 18 hours and 29 minutes
      • CREW: Cabana, Sturckow, Currie, Ross, Newman, Krikalev
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Installation of Endeavour's transfer tunnel adapter is complete. Strongbacks have been installed on the payload bay doors and the right hand radiators are deployed. Power converter unit electrical mates are in work today. Workers have resumed main engine heat shield work. Electrical system testing on Endeavour's orbiter docking system is slated through today. This afternoon freon coolant loop No. 2 will be deserviced.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Power converter unit interface verification test complete (Sept. 1)
      • Shuttle main engine installation complete (Sept. 4)

      MISSION: STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: Jan. 21, 1999 at 11:26 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Jan. 26, 1999 at 10:33 a.m. EST
      • LAUNCH WINDOW: 43 minutes
      • MISSION DURATION: 4 days, 23 hours, 7 minutes
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Functional checks of Columbia's fuel cells are complete. Troubleshooting of the fuel cell No. 2 pulse code modulator is under way. Technicians are also working to replace an overboard waste dump valve.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/