KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      MONDAY, AUGUST 31, 1998 (1:12 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax: 407-867-2692)

      Launch Viewing Information

      MISSION: STS-95 -- SPACEHAB-SM, SPARTAN & HOST

      STS-95 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: Oct. 29 at 2 p.m. EST
      • TARGET KSC LANDING DATE/TIME: Nov. 7 at 12:04 p.m. EST
      • MISSION DURATION: 8 days, 22 hours and 4 minutes
      • CREW: Brown, Lindsey, Parazynski, Robinson, Duque, Makai, Glenn
      • ORBITAL ALTITUDE and INCLINATION: 310 nautical miles/28.45 degrees

      NOTE: Over the weekend, workers completed installation of Discovery's main engine heat shields. Installation of the integrated vehicle health monitoring (IVHM) system brackets are complete and IVHM sensor installation is nearing completion. Today, technicians are conducting orbiter integrated hydraulic testing and preparing for tunnel adapter installation slated to occur later today. Closeouts of the orbiter's midbody compartment continue in preparation for Wednesday's Crew Equipment Interface Test. Testing of the Ku-band antenna continues. In high bay 1 of the Vehicle Assembly Building, external tank and solid rocket booster mating closeouts are ongoing.

      STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Crew Equipment Interface Test (Sept. 2)
      • Payload bay door closure (Sept. 8)
      • Orbiter roll over to VAB (Sept. 14)

      MISSION: STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION
      UNITY connecting module

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 at 4:45 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Dec. 14 at 11:14 p.m. EST
      • MISSION DURATION: 11 days, 18 hours and 29 minutes
      • CREW: Cabana, Sturckow, Currie, Ross, Newman, Krikalev
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Installation of the forward extension of Endeavour's transfer tunnel is complete. Connection of the orbiter docking system pyrotechnic devices and servicing of freon coolant loop No. 2 are also complete. Main engine heat shield inspections and the power converter unit interface verification test are in work.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Power converter unit IVT complete (Sept. 1)
      • Shuttle main engine installation (Sept. 10)

      MISSION: STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: Jan. 21, 1999 at 11:26 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Jan. 26, 1999 at 10:33 a.m. EST
      • LAUNCH WINDOW: 43 minutes
      • MISSION DURATION: 4 days, 23 hours, 7 minutes
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Troubleshooting of the fuel cell No. 2 pulse code modulator continues. Technicians are also working to replace an overboard waste dump valve.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/