STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)
NOTE: Shimming modifications of Columbia's payload bay aft bulkhead are complete. Today closeouts in the payload bay are under way and the payload bay doors will be closed Monday for the holiday down period. In the Vehicle Assembly Building, external tank and solid rocket booster closeouts continue.
STS-93 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-96 -- 2nd U.S. INTERNATIONAL SPACE STATION FLIGHTNOTE: Alcohol flushing of Discovery's auxiliary power units is complete. Workers are replacing the main engine No. 2 pitch actuator and replacing orbiter window No. 7 today. Next week, fuel cell voltage tests will be conducted. Discovery's payload bay doors will also be closed in preparation for the holiday down period.
STS-96 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-101 -- 3rd INTERNATIONAL SPACE STATION FLIGHTNOTE: Atlantis remains in VAB high bay 2 awaiting Columbia's move to the VAB in early January. OPF bay 3 will house Atlantis throughout the STS-101 processing flow. Workers have gained access to Atlantis' crew module to replace several ceiling panels during the temporary VAB storage period.
STS-99 -- SHUTTLE RADAR TOPOGRAPHY MISSION (SRTM)
NOTE: Endeavour is jacked and leveled in the OPF today, undergoing routine post-flight deservicing. Thorough inspections of the orbiter's exterior are complete, and engineers are reporting about 116 debris hits of which 25 are 1-inch or larger. Main engine bearing drying is complete and workers finished off-loading Endeavour's onboard cryogenics last night. Preparations are under way to open the orbiter's payload bay doors.
For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/